Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Replacement of 2003 Gillig Buses |
Description: Purchase 60 replacement buses to replace the fleet of 2003 Gillig buses thathave reached the end of their useful life
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Mateo |
City | San Carlos |
Zip Code | 94070 |
Senate District |
08, 11 |
Assembly District | 12, 19, 21 |
Congressional District | 12, 14 |
Caltrans District |
04 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 92 | 92 |
Project Contacts | Agency | Contact Person | Telephone | |
---|---|---|---|---|
PTMISEA |
REBECCA ARTHUR | (650) 508-6368 | ARTHURR@SAMTRANS.COM |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
|||||
Bond Funding | |||||||
PTMISEA-Interest |
$204 | $22 | $226 | ||||
PTMISEA-99314 |
$5,807 | $-2,184 | $3,622 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $20,721 | $20,721 | ||||
Local** |
$0 | $700 | $700 | ||||
Total**** | $6,011 | $19,259 | $25,269 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (06/30/2024 b=c-a |
Current Approved (06/30/2024 c |
Cost to Date** (06/30/2024 d |
Cost Forecast (06/30/2024 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $0 | $0 | $0 | $0 | $0 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$6,011 | $19,259 | $25,269 | $25,269 | $25,269 | $0 | |
Total* | $6,011 | $19,259 | $25,269 | $25,269 | $25,269 | $0 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (06/30/2024) c |
% Complete (06/30/2024) d |
Schedule Forecast (06/30/2024) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
01/01/2014 12/31/2016 |
02/24/2016 02/24/2016 |
02/01/2016 08/31/2017 |
100 | |
0 0 |
Begin Closeout Phase
End Closeout Phase |
01/31/2017 12/31/2017 |
03/01/2019 03/01/2019 |
11/30/2018 05/31/2019 |
0 | |
0 0 |
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Reduced Emissions | 92 | 92 |
Bond Funding Cost | |
---|---|
Adopted: |
$6,010,549 |
Current Approved: |
$3,622,168 |
Actual Expenditures: |
$3,622,168 |
Status as of June 30, 2024.
PTMISEA project sponsors are required to report semi-annually on project progress (GC Section 8879.50(f)(1)). Semi-annual reporting will reflect project status as of October 1 and December 31