Butte SR 99 Chico Auxilliary Lanes |
Description: In Chico, from SR 32 to East First Ave - Construct NB and SB auxillary lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Butte |
City | Chico |
Zip Code | 95926, 95928 |
Senate District |
04 |
Assembly District | 03 |
Congressional District | 02 |
Caltrans District |
03 |
County/State Route | Butte 99 |
Postmile Begin/End | R 32.4 R 33.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 87.7 | |
Lane Miles Added (Mixed) | 1.8 | |
Peak Period Time Savings (minutes) | 20684 | 2600 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Butte County Association of Governments | Andy Newsum | (530) 879-2468 | anewsum@bcag.com | |
Design (PS&E) Phase |
Butte County Association of Governments | Andy Newsum | (530) 879-2468 | anewsum@bcag.com | |
Right of Way Phase |
Butte County Association of Governments | Andy Newsum | (530) 879-2468 | anewsum@bcag.com | |
Construction Phase |
California Department of Transportation | Matt Solano | (530) 740-4805 | Matt_Solano@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Jeff Pulverman | (916) 274-0638 | jeff.pulverman@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,602 | $10,602 | ||||
BOND99 |
$23,520 | $-2,551 | $20,969 | ||||
Non-bond Funding | |||||||
State/Federal* |
$16,000 | $-11,372 | $4,628 | ||||
Local** |
$0 | $2,150 | $2,150 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $39,520 | $-1,171 | $38,349 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$0 | $0 | $0 | $0 | |||
Design(PS&E) |
$4,515 | $950 | $5,465 | $9,030 | |||
Right of Way |
$1,653 | $-453 | $1,200 | $0 | |||
Construction |
$33,352 | $-1,668 | $31,684 | $28,808 | |||
Total* | $39,520 | $-1,171 | $38,349 | $37,838 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2002 03/01/2005 |
|
01/01/2002 03/24/2005 |
100 | 01/01/2002 03/24/2005 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2007 07/01/2010 |
|
07/01/2007 05/10/2010 |
100 | 07/01/2007 05/10/2010 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2008 04/01/2011 |
|
05/01/2008 05/10/2010 |
100 | 05/01/2008 05/12/2010 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
01/01/2011 09/01/2013 |
|
01/15/2011 10/15/2013 |
100 | 07/08/2011 02/18/2015 |
-6 -16 |
|
Begin Closeout Phase
End Closeout Phase |
09/01/2014 09/01/2015 |
|
10/15/2013 10/15/2015 |
100 | 02/18/2015 06/24/2019 |
-16 -45 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2009 | 03/01/2009 | 0 | 06/03/2009 | -3 | ||
Implementation Date | 07/01/2010 | 07/01/2010 | 0 | 06/03/2009 | 13 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 87.7 | |
Lane Miles Added (Mixed) | 1.8 | |
Peak Period Time Savings (minutes) | 20684 | 2600 |
Bond Funding Cost | |
---|---|
Adopted: |
$23,520,000 |
Current Approved: |
$20,592,000 |
Actual Expenditures: |
$20,492,612 |
Status as of December 31, 2023.