Butte SR 99 Chico Auxilliary Lanes

Description: In Chico, from SR 32 to East First Ave - Construct NB and SB auxillary lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Chico
Zip Code 95926, 95928
 
Senate District
04
Assembly District 03
Congressional District 02
 
Caltrans District
03
 
 
County/State Route Butte 99
Postmile Begin/End R  32.4 R  33.3
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      87.7  
Lane Miles Added (Mixed)      1.8  
Peak Period Time Savings (minutes)  20684    2600  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Butte County Association of Governments Andy Newsum (530) 879-2468   anewsum@bcag.com
Design (PS&E) Phase
Butte County Association of Governments Andy Newsum (530) 879-2468   anewsum@bcag.com
Right of Way Phase
Butte County Association of Governments Andy Newsum (530) 879-2468   anewsum@bcag.com
Construction Phase
California Department of Transportation Matt Solano (530) 740-4805   Matt_Solano@dot.ca.gov
 
Corridor System Management Plan
Caltrans Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,602 $10,602
BOND99
$23,520 $-2,551 $20,969
Non-bond Funding
State/Federal*
$16,000 $-11,372 $4,628
Local**
$0 $2,150 $2,150
Non Budgeted ETC
$0 $0 $0
 
Total**** $39,520 $-1,171 $38,349

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$4,515 $950 $5,465 $9,030
Right of Way
$1,653 $-453 $1,200 $0
Construction
$33,352 $-1,668 $31,684 $28,808
 
Total* $39,520 $-1,171 $38,349 $37,838

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2002 

03/01/2005 
 

 
01/01/2002 

03/24/2005 
100  01/01/2002 

03/24/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

07/01/2010 
 

 
07/01/2007 

05/10/2010 
100  07/01/2007 

05/10/2010 


Begin Right of Way Phase

End Right of Way Phase
07/01/2008 

04/01/2011 
 

 
05/01/2008 

05/10/2010 
100  05/01/2008 

05/12/2010 


Begin Construction Phase

End Construction Phase
01/01/2011 

09/01/2013 
 

 
01/15/2011 

10/15/2013 
100  07/08/2011 

02/18/2015 
-6 

-16 
Begin Closeout Phase

End Closeout Phase
09/01/2014 

09/01/2015 
 

 
10/15/2013 

10/15/2015 
100  02/18/2015 

06/24/2019 
-16 

-45 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009  06/03/2009  -3 
Implementation Date 07/01/2010    07/01/2010  06/03/2009  13 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 87.7
Lane Miles Added (Mixed) 1.8
Peak Period Time Savings (minutes) 20684 2600

Bond Funding Cost
Adopted:
$23,520,000
Current Approved:
$20,592,000
Actual Expenditures:
$20,492,612

 

Status as of December 31, 2023.