SR 99/Elverta Rd. Interchange

Description: In Sacramento County on SR 99 at Elverta Road, construct interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elverta
Zip Code 95836
 
Senate District
06
Assembly District 05
Congressional District 03
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 35 36
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  6420    6420  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Sacramento County Stephen White 916-874-5354   whitest@saccounty.net
Design (PS&E) Phase
Sacramento County Stephen White 916-874-5354   whitest@saccounty.net
Right of Way Phase
Sacramento County Stephen White 916-874-5354   whitest@saccounty.net
Construction Phase
Sacramento County Stephen White 916-874-5354   whitest@saccounty.net
 
Corridor System Management Plan
Caltrans Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$19,110 $-581 $18,529
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$10,490 $3,451 $13,941
Non Budgeted ETC
$0 $0 $0
 
Total**** $29,600 $2,870 $32,470

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$400 $600 $1,000 $1,040
Design(PS&E)
$1,800 $0 $1,800 $1,280
Right of Way
$3,000 $1,400 $4,400 $4,400
Construction
$24,400 $870 $25,270 $24,757
 
Total* $29,600 $2,870 $32,470 $31,477

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

07/01/2009 
 

 
07/01/2007 

07/01/2009 
100  07/01/2007 

07/14/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

12/01/2010 
 

 
07/01/2009 

02/01/2012 
100  07/01/2009 

02/28/2012 


-1 
Begin Right of Way Phase

End Right of Way Phase
07/01/2009 

12/01/2010 
 

 
07/01/2009 

02/01/2012 
100  07/01/2009 

02/15/2012 


Begin Construction Phase

End Construction Phase
05/01/2011 

01/01/2013 
 

 
06/01/2012 

04/01/2014 
100  05/28/2012 

03/07/2014 


Begin Closeout Phase

End Closeout Phase
03/01/2013 

06/01/2013 
 

 
04/01/2014 

07/01/2014 
75  11/25/2015 

01/03/2019 
-20 

-55 
Corridor System Management Plan
Adoption Date 03/01/2009       
Implementation Date 07/01/2010       
????????
Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 6420 6420

Bond Funding Cost
Adopted:
$19,110,000
Current Approved:
$18,529,000
Actual Expenditures:
$18,529,000

 

Status as of December 31, 2023.