Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
SR 99/Elverta Rd. Interchange |
Description: In Sacramento County on SR 99 at Elverta Road, construct interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Elverta |
Zip Code | 95836 |
Senate District |
06 |
Assembly District | 05 |
Congressional District | 03 |
Caltrans District |
03 |
County/State Route | Sacramento 99 |
Postmile Begin/End | 35 36 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 6420 | 6420 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sacramento County | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Design (PS&E) Phase |
Sacramento County | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Right of Way Phase |
Sacramento County | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Construction Phase |
Sacramento County | Stephen White | 916-874-5354 | whitest@saccounty.net | |
Corridor System Management Plan |
Caltrans | Jeff Pulverman | (916) 274-0638 | jeff.pulverman@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$19,110 | $-581 | $18,529 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$10,490 | $3,451 | $13,941 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $29,600 | $2,870 | $32,470 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$400 | $600 | $1,000 | $1,040 | |||
Design(PS&E) |
$1,800 | $0 | $1,800 | $1,280 | |||
Right of Way |
$3,000 | $1,400 | $4,400 | $4,400 | |||
Construction |
$24,400 | $870 | $25,270 | $24,757 | |||
Total* | $29,600 | $2,870 | $32,470 | $31,477 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 07/01/2009 |
|
07/01/2007 07/01/2009 |
100 | 07/01/2007 07/14/2009 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2009 12/01/2010 |
|
07/01/2009 02/01/2012 |
100 | 07/01/2009 02/28/2012 |
0 -1 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2009 12/01/2010 |
|
07/01/2009 02/01/2012 |
100 | 07/01/2009 02/15/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
05/01/2011 01/01/2013 |
|
06/01/2012 04/01/2014 |
100 | 05/28/2012 03/07/2014 |
0 1 |
|
Begin Closeout Phase
End Closeout Phase |
03/01/2013 06/01/2013 |
|
04/01/2014 07/01/2014 |
75 | 11/25/2015 01/03/2019 |
-20 -55 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2009 | 0 | 0 | ||||
Implementation Date | 07/01/2010 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 6420 | 6420 |
Bond Funding Cost | |
---|---|
Adopted: |
$19,110,000 |
Current Approved: |
$18,529,000 |
Actual Expenditures: |
$18,529,000 |
Status as of December 31, 2023.