Add Aux Lane Calvine to north of Mack Rd on SR 99

Description: In Sacramento County, add auxiliary lanes from Calvine to Mack Road.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elk Grove, Sacramento
Zip Code 95823
 
Senate District
06
Assembly District 09, 10
Congressional District 05
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 16.8 18.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2914    3,251  
Peak Period Time Savings (minutes)  232092    258,881  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Doug Lange 530-741-4465   doug_lange@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Doug Lange 530-741-4465   doug_lange@dot.ca.gov
Right of Way Phase
Department of Transportation Doug Lange 530-741-4465   doug_lange@dot.ca.gov
Construction Phase
Department of Transportation Doug Lange 530-741-4465   doug_lange@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Jeff Pulverman (916) 274-0638   jeff.pulverman@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$6,860 $-1,054 $5,806
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$1,640 $0 $1,640
Non Budgeted ETC
$0 $0 $0
 
Total**** $8,500 $-1,054 $7,446

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$500 $-200 $300 $300
Design(PS&E)
$800 $0 $800 $805
Right of Way
$450 $-360 $90 $54
Construction
$6,750 $-494 $6,256 $6,045
 
Total* $8,500 $-1,054 $7,446 $7,205

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

01/01/2009 
 

 
05/01/2007 

01/15/2009 
100  05/01/2007 

01/15/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2008 

02/01/2010 
 

 
07/01/2008 

02/01/2009 
100  07/01/2008 

12/01/2009 


-10 
Begin Right of Way Phase

End Right of Way Phase
05/01/2009 

11/01/2010 
 

 
05/01/2009 

11/01/2010 
100  01/30/2009 

11/30/2010 


-1 
Begin Construction Phase

End Construction Phase
06/01/2010 

12/01/2011 
09/30/2010 

09/30/2010 
08/01/2012 

10/01/2012 
100  06/23/2010 

02/01/2013 
26 

-4 
Begin Closeout Phase

End Closeout Phase
12/01/2012 

12/01/2013 
09/30/2010 

09/30/2010 
10/01/2012 

10/01/2014 
50  02/01/2013 

09/29/2016 
-4 

-24 
Corridor System Management Plan
Adoption Date 03/01/2009    03/01/2009  03/01/2009 
Implementation Date 07/01/2010    07/01/2010  07/01/2010 
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2914 3,251
Peak Period Time Savings (minutes) 232092 258,881

Bond Funding Cost
Adopted:
$6,860,000
Current Approved:
$5,806,000
Actual Expenditures:
$5,800,000

 

Status as of December 31, 2023.