SR 99/Riego Road Interchange |
Description: In Sutter County, at SR 99 and Riego Road. Construct interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sutter |
City | Pleasant Grove, Sacramento |
Zip Code | 95668, 95836 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
03 |
County/State Route | Sutter 99 |
Postmile Begin/End | 0 2.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 65 hrs | 1082 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Sutter County | John Holder | (916) 274-0666 | john.holder@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Sung Moon | (530) 740-4805 | Sung.Moon@dot.ca.gov | |
Right of Way Phase |
Caltrans | Sung Moon | (530) 740-4805 | Sung.Moon@dot.ca.gov | |
Construction Phase |
Caltrans | Sung Moon | (530) 740-4805 | Sung.Moon@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Andrew Brandt | (530) 741-4337 | Andrew_Brandt@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$19,110 | $154 | $19,264 | ||||
Non-bond Funding | |||||||
Local** |
$11,730 | $88 | $11,818 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $30,840 | $242 | $31,082 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$340 | $180 | $520 | $473 | |||
Design(PS&E) |
$2,500 | $0 | $2,500 | $2,500 | |||
Right of Way |
$3,700 | $800 | $4,500 | $1,814 | |||
Construction |
$24,300 | $-738 | $23,562 | $26,306 | |||
Total* | $30,840 | $242 | $31,082 | $31,094 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/01/2000 12/01/2007 |
05/30/2007 05/30/2007 |
01/01/2000 12/01/2007 |
100 | 01/01/2000 11/29/2007 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2007 01/01/2011 |
05/30/2007 05/30/2007 |
12/01/2007 03/01/2012 |
100 | 12/01/2007 03/14/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
04/01/2009 09/01/2011 |
05/30/2007 05/30/2007 |
04/01/2009 06/01/2012 |
100 | 10/15/2008 01/26/2012 |
6 4 |
|
Begin Construction Phase
End Construction Phase |
05/01/2011 01/01/2013 |
05/30/2007 05/30/2007 |
07/01/2012 01/01/2015 |
75 | 10/01/2012 06/30/2015 |
-3 -6 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2014 01/01/2015 |
05/30/2007 05/30/2007 |
01/01/2015 01/01/2017 |
75 | 06/30/2015 07/31/2023 |
-6 -80 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 03/01/2009 | 0 | 0 | ||||
Implementation Date | 07/01/2010 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 65 hrs | 1082 |
Bond Funding Cost | |
---|---|
Adopted: |
$19,110,000 |
Current Approved: |
$19,264,000 |
Actual Expenditures: |
$19,202,000 |
Status as of December 31, 2023.