SR 99/Riego Road Interchange

Description: In Sutter County, at SR 99 and Riego Road. Construct interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter
City Pleasant Grove, Sacramento
Zip Code 95668, 95836
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
03
 
 
County/State Route Sutter 99
Postmile Begin/End 0 2.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  65 hrs    1082  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Sutter County John Holder (916) 274-0666   john.holder@dot.ca.gov
Design (PS&E) Phase
Caltrans Sung Moon (530) 740-4805   Sung.Moon@dot.ca.gov
Right of Way Phase
Caltrans Sung Moon (530) 740-4805   Sung.Moon@dot.ca.gov
Construction Phase
Caltrans Sung Moon (530) 740-4805   Sung.Moon@dot.ca.gov
 
Corridor System Management Plan
Caltrans Andrew Brandt (530) 741-4337   Andrew_Brandt@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$19,110 $154 $19,264
Non-bond Funding
Local**
$11,730 $88 $11,818
Non Budgeted ETC
$0 $0 $0
 
Total**** $30,840 $242 $31,082

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$340 $180 $520 $473
Design(PS&E)
$2,500 $0 $2,500 $2,500
Right of Way
$3,700 $800 $4,500 $1,814
Construction
$24,300 $-738 $23,562 $26,306
 
Total* $30,840 $242 $31,082 $31,094

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2000 

12/01/2007 
05/30/2007 

05/30/2007 
01/01/2000 

12/01/2007 
100  01/01/2000 

11/29/2007 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/01/2007 

01/01/2011 
05/30/2007 

05/30/2007 
12/01/2007 

03/01/2012 
100  12/01/2007 

03/14/2012 


Begin Right of Way Phase

End Right of Way Phase
04/01/2009 

09/01/2011 
05/30/2007 

05/30/2007 
04/01/2009 

06/01/2012 
100  10/15/2008 

01/26/2012 


Begin Construction Phase

End Construction Phase
05/01/2011 

01/01/2013 
05/30/2007 

05/30/2007 
07/01/2012 

01/01/2015 
75  10/01/2012 

06/30/2015 
-3 

-6 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

01/01/2015 
05/30/2007 

05/30/2007 
01/01/2015 

01/01/2017 
75  06/30/2015 

07/31/2023 
-6 

-80 
Corridor System Management Plan
Adoption Date 03/01/2009       
Implementation Date 07/01/2010       
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 65 hrs 1082

Bond Funding Cost
Adopted:
$19,110,000
Current Approved:
$19,264,000
Actual Expenditures:
$19,202,000

 

Status as of December 31, 2023.