Sutter 99 Segment 2

Description: In Sutter County from 0.2 mile north of Power Line Rd to 0.6 mile north of Sacramento Ave; Widen highway to a 4-lane expressway with a continuous 12-foot wide median left-turn lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter
City Nicolaus, Rio Oso, Yuba City
Zip Code 95659, 95674, 95991
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
03
 
 
County/State Route Sutter 99
Postmile Begin/End 11 14.3
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)      6.4  
Pavement Lane Miles  6.6      
Peak Period Time Savings (minutes)      1010  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Winder Bajwa (530) 741-4432   winder_bajwa@dot.ca.gov
Design (PS&E) Phase
Caltrans Winder Bajwa (530) 741-4432   winder_bajwa@dot.ca.gov
Right of Way Phase
Caltrans Winder Bajwa (530) 741-4432   winder_bajwa@dot.ca.gov
Construction Phase
Caltrans Winder Bajwa (530) 741-4432   winder_bajwa@dot.ca.gov
 
Corridor System Management Plan
Caltrans Andrew Brandt (530) 741-4337   Andrew_Brandt@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$73,500 $-22,710 $50,790
Non-bond Funding
State/Federal*
$0 $1,723 $1,723
Local**
$3,100 $-1,309 $1,791
Non Budgeted ETC
$0 $0 $0
 
Total**** $76,600 $-22,296 $54,304

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$3,600 $-1,086 $2,514 $2,204
Right of Way
$4,000 $-2,020 $1,980 $1,974
Construction
$69,000 $-19,190 $49,810 $49,803
 
Total* $76,600 $-22,296 $54,304 $53,982

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

03/01/2004 
05/30/2007 

05/30/2007 
06/01/1999 

03/01/2004 
100  06/01/2000 

03/12/2004 
-12 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
11/01/2006 

04/01/2009 
05/30/2007 

05/30/2007 
11/01/2006 

04/01/2009 
100  11/01/2006 

06/26/2009 


-3 
Begin Right of Way Phase

End Right of Way Phase
04/01/2007 

04/01/2009 
05/30/2007 

05/30/2007 
04/01/2007 

04/01/2009 
100  04/25/2007 

04/01/2009 
-1 

Begin Construction Phase

End Construction Phase
07/01/2009 

05/01/2012 
05/30/2007 

05/30/2007 
07/01/2009 

05/01/2012 
50  07/14/2010 

05/15/2015 
-13 

-37 
Begin Closeout Phase

End Closeout Phase
05/01/2013 

05/01/2014 
05/30/2007 

05/30/2007 
05/01/2013 

05/01/2014 
100  09/30/2015 

12/01/2016 
-29 

-31 
Corridor System Management Plan
Adoption Date 06/03/2009    06/03/2009   
Implementation Date 06/03/2009    06/03/2009   
????????
Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 6.4
Pavement Lane Miles 6.6
Peak Period Time Savings (minutes) 1010

Bond Funding Cost
Adopted:
$73,500,000
Current Approved:
$56,725,000
Actual Expenditures:
$53,962,000

 

Status as of December 31, 2023.