Island Park 6-Lane

Description: In Fresno and Madera counties and in and near the City of Fresno, from Ashlan Ave to Avenue 7, widen 4-lane freeway to 6-lane freeway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno, Madera
City Fresno
Zip Code 93637, 93722
 
Senate District
14
Assembly District 29, 31
Congressional District 18, 19
 
Caltrans District
06
 
 
County/State Route Madera 99
Postmile Begin/End 0 1.6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  1795    1795  
Peak Period Time Savings (minutes)  42881    42881  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Design (PS&E) Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Right of Way Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Construction Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
 
Corridor System Management Plan
Caltrans Steve Curti (559) 488-4162   steve.curti@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$93,000 $-7,073 $85,927
Non-bond Funding
Local**
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $93,000 $-7,073 $85,927

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$2,300 $537 $2,837 $3,327
Design(PS&E)
$5,800 $-1,334 $4,466 $5,764
Right of Way
$2,300 $3,596 $5,896 $4,169
Construction
$82,600 $-9,872 $72,728 $72,349
 
Total* $93,000 $-7,073 $85,927 $85,609

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

04/01/2010 
 

 
07/01/2007 

04/01/2010 
100  05/01/2007 

07/22/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2009 

03/01/2012 
 

 
05/01/2009 

03/01/2012 
100   

09/30/2009 


29 
Begin Right of Way Phase

End Right of Way Phase
10/01/2009 

05/01/2012 
 

 
10/01/2009 

05/01/2012 
100  05/01/2009 

 


Begin Construction Phase

End Construction Phase
09/01/2012 

07/01/2016 
 

 
09/01/2012 

07/01/2016 
100  08/10/2010 

02/03/2012 
25 

54 
Begin Closeout Phase

End Closeout Phase
07/01/2016 

07/01/2018 
 

 
07/01/2016 

07/01/2018 
100   

02/06/2013 


66 
Corridor System Management Plan
Adoption Date 04/01/2009       
Implementation Date 10/01/2009       
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1795 1795
Peak Period Time Savings (minutes) 42881 42881

Bond Funding Cost
Adopted:
$93,000,000
Current Approved:
$23,220,000
Actual Expenditures:
$22,304,000

 

Status as of December 31, 2023.