Reconstruct Interchange @ Ave 12 |
Description: In Madera County from 0.2 mile south of Avenue 12 overcrossing to 0.3 mile north of Avenue 12 overcrossing. Reconstruct interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera |
City | Madera |
Zip Code | 93637 |
Senate District |
12, 14 |
Assembly District | 29 |
Congressional District | 19 |
Caltrans District |
06 |
County/State Route | Madera 99 |
Postmile Begin/End | R 7.1 R 7.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 32 | 37 |
Peak Period Time Savings (minutes) | 2533 | 2940 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Jim Bane | (559) 243-3469 | jim.bane@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Jim Bane | (559) 243-3469 | jim.bane@dot.ca.gov | |
Right of Way Phase |
Caltrans | Jim Bane | (559) 243-3469 | jim.bane@dot.ca.gov | |
Construction Phase |
Caltrans | Jim Bane | (559) 243-3469 | jim.bane@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Steve Curti | (559) 488-4162 | steve.curti@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $5,547 | $5,547 | ||||
BOND99 |
$48,400 | $6,666 | $55,066 | ||||
Non-bond Funding | |||||||
State/Federal* |
$8,023 | $9,253 | $17,276 | ||||
Local** |
$11,577 | $0 | $11,577 | ||||
Total**** | $68,000 | $21,466 | $89,466 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,300 | $700 | $2,000 | $1,994 | |||
Design(PS&E) |
$4,700 | $-700 | $4,000 | $5,215 | |||
Right of Way |
$7,200 | $23,800 | $31,000 | $37,725 | |||
Construction |
$54,800 | $-2,334 | $52,466 | $51,716 | |||
Total* | $68,000 | $21,466 | $89,466 | $96,649 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 09/01/2009 |
|
06/01/2007 09/01/2009 |
100 | 06/01/2007 09/24/2009 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2009 05/01/2012 |
|
07/01/2009 05/01/2012 |
100 | 07/01/2009 06/20/2012 |
0 -2 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/01/2009 07/01/2012 |
|
09/01/2009 07/01/2012 |
0 | 09/01/2009 06/20/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
10/01/2012 11/01/2015 |
|
10/01/2012 11/01/2015 |
0 | 12/07/2012 06/13/2016 |
-2 -7 |
|
Begin Closeout Phase
End Closeout Phase |
11/01/2015 08/01/2017 |
|
11/01/2015 08/01/2017 |
100 | 06/16/2016 08/01/2023 |
-8 -73 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 04/01/2009 | 04/01/2009 | 0 | 0 | |||
Implementation Date | 10/01/2009 | 10/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 32 | 37 |
Peak Period Time Savings (minutes) | 2533 | 2940 |
Bond Funding Cost | |
---|---|
Adopted: |
$48,400,000 |
Current Approved: |
$59,402,000 |
Actual Expenditures: |
$55,054,000 |
Status as of December 31, 2023.