Reconstruct Interchange @ Ave 12

Description: In Madera County from 0.2 mile south of Avenue 12 overcrossing to 0.3 mile north of Avenue 12 overcrossing. Reconstruct interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12, 14
Assembly District 29
Congressional District 19
 
Caltrans District
06
 
 
County/State Route Madera 99
Postmile Begin/End R  7.1 R  7.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  32    37  
Peak Period Time Savings (minutes)  2533    2940  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Design (PS&E) Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Right of Way Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
Construction Phase
Caltrans Jim Bane (559) 243-3469   jim.bane@dot.ca.gov
 
Corridor System Management Plan
Caltrans Steve Curti (559) 488-4162   steve.curti@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $5,547 $5,547
BOND99
$48,400 $6,666 $55,066
Non-bond Funding
State/Federal*
$8,023 $9,253 $17,276
Local**
$11,577 $0 $11,577
 
Total**** $68,000 $21,466 $89,466

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,300 $700 $2,000 $1,994
Design(PS&E)
$4,700 $-700 $4,000 $5,215
Right of Way
$7,200 $23,800 $31,000 $37,725
Construction
$54,800 $-2,334 $52,466 $51,716
 
Total* $68,000 $21,466 $89,466 $96,649

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

09/01/2009 
 

 
06/01/2007 

09/01/2009 
100  06/01/2007 

09/24/2009 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2009 

05/01/2012 
 

 
07/01/2009 

05/01/2012 
100  07/01/2009 

06/20/2012 


-2 
Begin Right of Way Phase

End Right of Way Phase
09/01/2009 

07/01/2012 
 

 
09/01/2009 

07/01/2012 
09/01/2009 

06/20/2012 


Begin Construction Phase

End Construction Phase
10/01/2012 

11/01/2015 
 

 
10/01/2012 

11/01/2015 
12/07/2012 

06/13/2016 
-2 

-7 
Begin Closeout Phase

End Closeout Phase
11/01/2015 

08/01/2017 
 

 
11/01/2015 

08/01/2017 
100  06/16/2016 

08/01/2023 
-8 

-73 
Corridor System Management Plan
Adoption Date 04/01/2009    04/01/2009   
Implementation Date 10/01/2009    10/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 32 37
Peak Period Time Savings (minutes) 2533 2940

Bond Funding Cost
Adopted:
$48,400,000
Current Approved:
$59,402,000
Actual Expenditures:
$55,054,000

 

Status as of December 31, 2023.