Goshen to Kingsburg 6-Lane

Description: In Tulare and Fresno Counties from the Goshen Overhead to Route 201. Widen from 4-lane to 6-lane freeway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Goshen, Kingsburg, Traver
Zip Code 93291, 93631
 
Senate District
16
Assembly District 30
Congressional District 21
 
Caltrans District
06
 
 
County/State Route Tulare 99
Postmile Begin/End 41.3 R  53.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      1608  
Lane Miles Added (Mixed)  20.3    20.3  
Peak Period Time Savings (minutes)      128079  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Phillip Sanchez (559) 243-3466   phillip.sanchez@dot.ca.gov
Design (PS&E) Phase
Caltrans Phillip Sanchez (559) 243-3466   phillip.sanchez@dot.ca.gov
Right of Way Phase
Caltrans Phillip Sanchez (559) 243-3466   phillip.sanchez@dot.ca.gov
Construction Phase
Caltrans Phillip Sanchez (559) 243-3466   phillip.sanchez@dot.ca.gov
 
Corridor System Management Plan
Caltrans Paul-Albert Marquez (559) 445-5867   paul-albert.marquez@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$156,400 $-55,776 $100,624
Non-bond Funding
State/Federal*
$2,202 $188 $2,390
Local**
$14,034 $-1,654 $12,380
Non Budgeted ETC
$0 $0 $0
 
Total**** $172,636 $-57,242 $115,394

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$2,202 $188 $2,390 $2,383
Design(PS&E)
$8,000 $-950 $7,050 $7,324
Right of Way
$2,434 $710 $3,144 $3,260
Construction
$160,000 $-57,190 $102,810 $103,665
 
Total* $172,636 $-57,242 $115,394 $115,600

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2001 

11/01/2006 
 

 
07/01/2001 

11/01/2006 
100  07/01/2001 

11/01/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2007 

02/01/2010 
 

 
07/01/2007 

02/01/2010 
100  07/01/2007 

04/30/2010 


-3 
Begin Right of Way Phase

End Right of Way Phase
10/01/2007 

03/01/2010 
 

 
10/01/2007 

03/01/2010 
100  10/01/2007 

04/28/2010 


-2 
Begin Construction Phase

End Construction Phase
07/01/2010 

08/01/2013 
09/30/2010 

01/30/2018 
07/01/2010 

08/01/2013 
01/04/2011 

11/02/2015 
-6 

-27 
Begin Closeout Phase

End Closeout Phase
08/01/2013 

08/01/2014 
09/30/2010 

01/30/2018 
08/01/2013 

08/01/2014 
100  11/02/2015 

08/02/2022 
-27 

-97 
Corridor System Management Plan
Adoption Date 08/01/2008    08/01/2008   
Implementation Date 04/01/2009    04/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 1608
Lane Miles Added (Mixed) 20.3 20.3
Peak Period Time Savings (minutes) 128079

Bond Funding Cost
Adopted:
$156,400,000
Current Approved:
$4,944,000
Actual Expenditures:
$4,279,000

 

Status as of December 31, 2023.