Arboleda Road Freeway

Description: Near Merced on Route 99 from Buchanan Hollow Road to Miles Creek Overflow. Convert to 6-lane freeway and construct interchange at Arboleda Road. (TCRP #104)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Merced
City Le Grand, Merced
Zip Code 95333, 95340
 
Senate District
12
Assembly District 17
Congressional District 18
 
Caltrans District
10
 
 
County/State Route Merced 99
Postmile Begin/End 4.6 10.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  87    85  
Lane Miles Added (Mixed)  16.2    16.2  
Peak Period Time Savings (minutes)  6951    6752  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Design (PS&E) Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Right of Way Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Construction Phase
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
 
Corridor System Management Plan
Department of Transportation Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$140,300 $-62,068 $78,232
Non-bond Funding
State/Federal*
$36,487 $-154 $36,333
Non Budgeted ETC
$0 $0 $0
 
Total**** $176,787 $-62,222 $114,565

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$4,917 $0 $4,917 $4,104
Design(PS&E)
$6,400 $-495 $5,905 $5,682
Right of Way
$26,470 $0 $26,470 $20,615
Construction
$139,000 $-61,727 $77,273 $77,254
 
Total* $176,787 $-62,222 $114,565 $107,654

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1999 

06/01/2006 
 

 
07/01/1999 

06/01/2006 
100  07/01/1999 

06/30/2006 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2007 

05/25/2011 
 

 
04/01/2007 

05/25/2011 
100  11/01/2006 

05/25/2011 


Begin Right of Way Phase

End Right of Way Phase
09/01/2007 

10/27/2011 
 

 
09/01/2007 

10/27/2011 
100  04/02/2007 

05/16/2011 


Begin Construction Phase

End Construction Phase
04/01/2012 

04/01/2015 
 

 
04/01/2012 

04/01/2015 
100  04/06/2012 

05/18/2015 


-2 
Begin Closeout Phase

End Closeout Phase
05/01/2015 

05/01/2016 
 

 
05/01/2015 

05/01/2016 
100  07/06/2015 

12/30/2016 
-2 

-8 
Corridor System Management Plan
Adoption Date 10/01/2008       
Implementation Date 02/01/2009       
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 87 85
Lane Miles Added (Mixed) 16.2 16.2
Peak Period Time Savings (minutes) 6951 6752

Bond Funding Cost
Adopted:
$140,300,000
Current Approved:
$91,319,000
Actual Expenditures:
$78,008,000

 

Status as of December 31, 2023.