SR 99 (South Stockton) Widening |
Description: In San Joaquin County from 0.3 mile north of Arch Rd to 0.1 mile south of Route 4 West. Widen from 4 to 6 lanes and improve and/or reconstruct various interchanges.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Stockton |
Zip Code | 95201, 95205 |
Senate District |
05 |
Assembly District | 26 |
Congressional District | 11, 18 |
Caltrans District |
10 |
County/State Route | San Joaquin 99 |
Postmile Begin/End | 15 18.6 |
County/State Route | San Joaquin 04 |
Postmile Begin/End | |
County/State Route | San Joaquin 04 |
Postmile Begin/End | |
County/State Route | San Joaquin 4 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 4722 | 4833 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 7.2 | |
Pavement Lane Miles | 7.2 | |
Peak Period Time Savings (minutes) | 376053 | 384915 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | John Thomas | (559 408-4496 | john.thomas@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Tom Garibay | (559) 974-4139 | tom.garibay@dot.ca.gov | |
Right of Way Phase |
Caltrans | Anupam Mishra | (209) 948-7856 | anupam.mishra@dot.ca.gov | |
Construction Phase |
Caltrans | Pam Marquez | (209) 948-3971 | pam.marquez@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Sam Shankar | (209) 639-6456 | udaya.shankar@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$153,900 | $-25,744 | $128,156 | ||||
SLPP |
$0 | $16,065 | $16,065 | ||||
Non-bond Funding | |||||||
State/Federal* |
$14,581 | $4,000 | $18,581 | ||||
Local** |
$82,019 | $-34,463 | $47,556 | ||||
Total**** | $250,500 | $-40,142 | $210,358 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,081 | $2,949 | $6,030 | $5,916 | |||
Design(PS&E) |
$3,319 | $8,681 | $12,000 | $12,415 | |||
Right of Way |
$74,600 | $-18,230 | $56,370 | $45,139 | |||
Construction |
$169,500 | $-33,542 | $135,958 | $125,635 | |||
Total* | $250,500 | $-40,142 | $210,358 | $189,104 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
04/01/2006 12/01/2008 |
04/07/2006 10/28/2008 |
04/07/2006 12/01/2008 |
100 | 04/07/2006 11/15/2008 |
0 1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/01/2008 02/01/2012 |
12/15/2008 06/04/2012 |
12/01/2008 06/01/2012 |
100 | 12/15/2008 06/04/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
01/01/2009 01/01/2012 |
02/01/2008 03/01/2012 |
12/01/2008 03/01/2012 |
96 | 12/15/2008 03/01/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/01/2012 06/01/2015 |
10/06/2012 09/20/2017 |
11/01/2012 06/01/2016 |
0 | 12/03/2012 09/20/2017 |
-1 -16 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2017 02/01/2017 |
01/31/2022 10/31/2023 |
06/02/2017 08/02/2018 |
96 | 05/31/2017 01/31/2022 |
0 -43 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2008 | 0 | 0 | ||||
Implementation Date | 02/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 4722 | 4833 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 7.2 | |
Pavement Lane Miles | 7.2 | |
Peak Period Time Savings (minutes) | 376053 | 384915 |
Bond Funding Cost | |
---|---|
Adopted: |
$153,900,000 |
Current Approved: |
$132,256 |
Actual Expenditures: |
$112,424 |
Status as of December 31, 2023.