SR 99 Widening in Manteca and San Joaquin

Description: In San Joaquin County, in Manteca, from SR 120 West to 0.4 mile north of Arch Road. Widen SR 99 from 4 to 6 lanes. Construct frontage rds, replace overcrossings, etc.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Joaquin
City Manteca, Stockton
Zip Code 95206, 95215, 95336
 
Senate District
05
Assembly District 17
Congressional District 11
 
Caltrans District
10
 
 
County/State Route San Joaquin 99
Postmile Begin/End 5.3 15
 
County/State Route San Joaquin 99
Postmile Begin/End
 
County/State Route San Joaquin 99
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  12592      
Pavement Lane Miles  16.8      
Peak Period Time Savings (minutes)  1002757      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
SJCOG Kevin Sheridan (209) 948-3930   ksheridan@sjcog.org
Design (PS&E) Phase
SJCOG Kevin sheridan (209) 948-3930   ksheridan@sjcog.org
Right of Way Phase
Caltrans James Gonzalez (559) 445-6219   james.gonzalez@dot.ca.gov
Construction Phase
Caltrans Pam Marquez (209) 948-3971   pam.marquez@dot.ca.gov
 
Corridor System Management Plan
Caltrans Sam Shankar (209) 639-6456   udaya.shankar@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $24,984 $24,984
BOND99
$133,000 $-50,795 $82,205
Non-bond Funding
State/Federal*
$4,500 $3,285 $7,785
Local**
$112,500 $-78,965 $33,535
Non Budgeted ETC
$0 $0 $0
 
Total**** $250,000 $-101,491 $148,509

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,600 $-36 $3,564 $3,635
Design(PS&E)
$8,000 $9,910 $17,910 $19,108
Right of Way
$15,200 $6,373 $21,573 $20,102
Construction
$223,200 $-117,738 $105,462 $102,630
 
Total* $250,000 $-101,491 $148,509 $145,475

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2007 

02/01/2010 
 

 
07/01/2007 

03/18/2010 
100  07/01/2007 

03/18/2010 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

10/01/2011 
 

 
01/04/2010 

12/07/2011 
100  01/04/2010 

05/06/2011 


Begin Right of Way Phase

End Right of Way Phase
12/01/2010 

09/01/2011 
 

 
03/15/2010 

06/01/2011 
100  03/15/2010 

03/28/2011 


Begin Construction Phase

End Construction Phase
03/01/2012 

07/01/2015 
 

 
03/27/2012 

07/01/2014 
100   

 


Begin Closeout Phase

End Closeout Phase
02/01/2016 

06/01/2017 
 

 
07/01/2014 

07/01/2015 
75   

 


Corridor System Management Plan
Adoption Date 10/01/2008       
Implementation Date 02/01/2009       
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 12592
Pavement Lane Miles 16.8
Peak Period Time Savings (minutes) 1002757

Bond Funding Cost
Adopted:
$133,000,000
Current Approved:
$89,790,000
Actual Expenditures:
$80,799,000

 

Status as of December 31, 2023.