SR 99 Widening in Manteca and San Joaquin |
Description: In San Joaquin County, in Manteca, from SR 120 West to 0.4 mile north of Arch Road. Widen SR 99 from 4 to 6 lanes. Construct frontage rds, replace overcrossings, etc.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Joaquin |
City | Manteca, Stockton |
Zip Code | 95206, 95215, 95336 |
Senate District |
05 |
Assembly District | 17 |
Congressional District | 11 |
Caltrans District |
10 |
County/State Route | San Joaquin 99 |
Postmile Begin/End | 5.3 15 |
County/State Route | San Joaquin 99 |
Postmile Begin/End | |
County/State Route | San Joaquin 99 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 12592 | |
Pavement Lane Miles | 16.8 | |
Peak Period Time Savings (minutes) | 1002757 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
SJCOG | Kevin Sheridan | (209) 948-3930 | ksheridan@sjcog.org | |
Design (PS&E) Phase |
SJCOG | Kevin sheridan | (209) 948-3930 | ksheridan@sjcog.org | |
Right of Way Phase |
Caltrans | James Gonzalez | (559) 445-6219 | james.gonzalez@dot.ca.gov | |
Construction Phase |
Caltrans | Pam Marquez | (209) 948-3971 | pam.marquez@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Sam Shankar | (209) 639-6456 | udaya.shankar@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $24,984 | $24,984 | ||||
BOND99 |
$133,000 | $-50,795 | $82,205 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,500 | $3,285 | $7,785 | ||||
Local** |
$112,500 | $-78,965 | $33,535 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $250,000 | $-101,491 | $148,509 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,600 | $-36 | $3,564 | $3,635 | |||
Design(PS&E) |
$8,000 | $9,910 | $17,910 | $19,108 | |||
Right of Way |
$15,200 | $6,373 | $21,573 | $20,102 | |||
Construction |
$223,200 | $-117,738 | $105,462 | $102,630 | |||
Total* | $250,000 | $-101,491 | $148,509 | $145,475 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2007 02/01/2010 |
|
07/01/2007 03/18/2010 |
100 | 07/01/2007 03/18/2010 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2010 10/01/2011 |
|
01/04/2010 12/07/2011 |
100 | 01/04/2010 05/06/2011 |
0 7 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/01/2010 09/01/2011 |
|
03/15/2010 06/01/2011 |
100 | 03/15/2010 03/28/2011 |
0 2 |
|
Begin Construction Phase
End Construction Phase |
03/01/2012 07/01/2015 |
|
03/27/2012 07/01/2014 |
100 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2016 06/01/2017 |
|
07/01/2014 07/01/2015 |
75 | |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/01/2008 | 0 | 0 | ||||
Implementation Date | 02/01/2009 | 0 | 0 |
????????
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 12592 | |
Pavement Lane Miles | 16.8 | |
Peak Period Time Savings (minutes) | 1002757 |
Bond Funding Cost | |
---|---|
Adopted: |
$133,000,000 |
Current Approved: |
$89,790,000 |
Actual Expenditures: |
$80,799,000 |
Status as of December 31, 2023.