State Route 99/113 Interchange

Description: In Sutter County near Tudor from just north of Railroad Avenue to 1.0 mile south of O'Banion Road. Construct interchange at the intersetion of SR 113 and SR 99.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter
City Yuba City
Zip Code 95991, 95993
 
Senate District
04
Assembly District 03
Congressional District 03
 
Caltrans District
03
 
 
County/State Route Sutter 99
Postmile Begin/End 15.9 17.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      304  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)      24218  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sung Moon (530)740-4805   sung_moon@dot.ca.gov
Design (PS&E) Phase
Caltrans Sung Moon (530)740-4805   sung_moon@dot.ca.gov
Right of Way Phase
Caltrans Sung Moon (530)740-4805   sung_moon@dot.ca.gov
Construction Phase
Caltrans Sung Moon (530)740-4805   sung_moon@dot.ca.gov
 
Corridor System Management Plan
Caltrans Andrew Brandt (530)741-4337   Andrew_Brandt@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$17,750 $-2,406 $15,344
Non-bond Funding
State/Federal*
$1,600 $300 $1,900
Non Budgeted ETC
$0 $0 $0
 
Total**** $19,350 $-2,106 $17,244

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$0 $0 $0 $0
Design(PS&E)
$1,000 $300 $1,300 $1,341
Right of Way
$600 $0 $600 $1,133
Construction
$17,750 $-2,406 $15,344 $15,297
 
Total* $19,350 $-2,106 $17,244 $17,772

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

03/12/2004 
 

 
06/01/1999 

03/12/2004 
06/01/1999 

03/12/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/01/2011 

07/15/2012 
 

10/10/2011 
06/01/2011 

07/15/2012 
100  08/01/2011 

06/18/2012 
-2 

Begin Right of Way Phase

End Right of Way Phase
06/01/2011 

07/15/2012 
 

10/10/2011 
06/01/2011 

07/15/2012 
25  04/14/2011 

06/07/2012 


Begin Construction Phase

End Construction Phase
11/01/2012 

12/01/2014 
 

 
11/01/2012 

12/01/2014 
100  10/16/2012 

08/07/2014 


Begin Closeout Phase

End Closeout Phase
12/01/2014 

12/01/2016 
 

 
12/14/2014 

12/01/2016 
100  08/07/2014 

12/01/2015 


12 
Corridor System Management Plan
Adoption Date 01/05/2007    01/05/2007  01/05/2007 
Implementation Date 06/30/2009    06/30/2009  06/30/2009 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 304
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 24218

Bond Funding Cost
Adopted:
$17,750,000
Current Approved:
$16,333,000
Actual Expenditures:
$14,895,231

 

Status as of December 31, 2023.