South Bakersfield 8-Lane Widening

Description: In Bakersfield, from 0.5 mile south of Route 119 to Wilson Road. Widen from 6 lanes to 8 lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
 
County/State Route Kern 99
Postmile Begin/End 17 22.1
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3061    3,265  
Lane Miles Added (Mixed)      10.2  
Peak Period Time Savings (minutes)  117240    77,999  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Paul Pineda (661) 326-3416   paul_pineda@dot.ca.gov
Design (PS&E) Phase
Caltrans Paul Pineda (661) 326-3416   paul_pineda@dot.ca.gov
Right of Way Phase
Caltrans Paul Pineda (661) 326-3416   paul_pineda@dot.ca.gov
Construction Phase
Caltrans Paul Pineda (661) 326-3416   paul_pineda@dot.ca.gov
 
Corridor System Management Plan
Caltrans Paul Pineda (661) 326-3416   paul_pineda@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$31,100 $-6,720 $24,380
Non-bond Funding
State/Federal*
$2,700 $0 $2,700
Local**
$50 $0 $50
Non Budgeted ETC
$0 $0 $0
 
Total**** $33,850 $-6,720 $27,130

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,600 $0 $1,600 $1,535
Design(PS&E)
$1,100 $0 $1,100 $1,112
Right of Way
$50 $0 $50 $10
Construction
$31,100 $-6,720 $24,380 $24,379
 
Total* $33,850 $-6,720 $27,130 $27,036

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2010 

08/01/2011 
 

 
07/01/2010 

08/01/2011 
100  11/05/2010 

08/01/2011 
-4 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
08/01/2011 

05/25/2012 
 

 
08/01/2011 

05/25/2012 
100  08/01/2011 

05/25/2012 


Begin Right of Way Phase

End Right of Way Phase
08/01/2011 

05/25/2012 
 

 
08/01/2011 

05/25/2012 
100  09/15/2011 

05/21/2012 
-1 

Begin Construction Phase

End Construction Phase
10/01/2012 

11/15/2014 
 

 
10/01/2012 

11/15/2014 
100  10/24/2012 

09/18/2014 
-1 

Begin Closeout Phase

End Closeout Phase
11/15/2014 

11/15/2016 
 

 
11/15/2014 

11/15/2016 
09/18/2014 

03/01/2017 


-4 
Corridor System Management Plan
Adoption Date 04/28/2009    01/08/2009  04/28/2009  -4 
Implementation Date 05/28/2009    05/28/2009  05/25/2009 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3061 3,265
Lane Miles Added (Mixed) 10.2
Peak Period Time Savings (minutes) 117240 77,999

Bond Funding Cost
Adopted:
$31,100,000
Current Approved:
$24,600,000
Actual Expenditures:
$24,380,000

 

Status as of December 31, 2023.