North Bakersfield Widening |
Description: In Bakersfield, from Route 204 to Beardsley Canal Bridge. Widen from 6 lanes to 8 lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
06 |
County/State Route | Kern 99 |
Postmile Begin/End | 27 28.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1510 | 1,510 |
Lane Miles Added (Mixed) | 2.8 | |
Peak Period Time Savings (minutes) | 2,533 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Paul Pineda | (661)326-3416 | paul_pineda@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Paul Pineda | (661)326-3416 | paul_pineda@dot.ca.gov | |
Right of Way Phase |
Caltrans | Paul Pineda | (661)326-3416 | paul_pineda@dot.ca.gov | |
Construction Phase |
Caltrans | Paul Pineda | (661)326-3416 | paul_pineda@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Paul Pineda | (661)326-3416 | paul_pineda@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$11,300 | $-2,446 | $8,854 | ||||
Non-bond Funding | |||||||
State/Federal* |
$1,200 | $0 | $1,200 | ||||
Local** |
$0 | $0 | $0 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $12,500 | $-2,446 | $10,054 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$515 | $0 | $515 | $533 | |||
Design(PS&E) |
$685 | $0 | $685 | $656 | |||
Right of Way |
$0 | $0 | $0 | $2 | |||
Construction |
$11,300 | $-2,446 | $8,854 | $8,853 | |||
Total* | $12,500 | $-2,446 | $10,054 | $10,045 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
07/01/2010 08/01/2011 |
|
07/01/2010 08/01/2011 |
100 | 10/20/2010 08/01/2011 |
-3 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2011 04/24/2012 |
|
08/01/2011 04/24/2012 |
100 | 08/01/2011 04/24/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
08/01/2011 01/30/2012 |
|
08/01/2011 01/30/2012 |
100 | 09/01/2011 01/30/2012 |
-1 0 |
|
Begin Construction Phase
End Construction Phase |
12/15/2012 12/01/2013 |
|
12/15/2012 12/01/2013 |
100 | 02/21/2012 07/10/2014 |
10 -7 |
|
Begin Closeout Phase
End Closeout Phase |
12/01/2013 12/01/2015 |
|
12/01/2013 12/01/2015 |
0 | 07/10/2014 07/01/2017 |
-7 -19 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 1510 | 1,510 |
Lane Miles Added (Mixed) | 2.8 | |
Peak Period Time Savings (minutes) | 2,533 |
Bond Funding Cost | |
---|---|
Adopted: |
$11,300,000 |
Current Approved: |
$9,000,000 |
Actual Expenditures: |
$8,854,000 |
Status as of December 31, 2023.