Elk Grove Boulevard / SR 99 Interchange Modification

Description: In Elk Grove at Elk Grove Boulevard. Add northbound on-ramp, remove existing traffic signal, add second left turn lane to southbound on-ramp, and add northbound deceleration lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elk Grove
Zip Code
 
Senate District
01
Assembly District 15
Congressional District 03
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 12.3 12.9
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  630    650  
Lane Miles Added (HOV)      0  
Lane Miles Added (Mixed)      0  
Peak Period Time Savings (minutes)  25750    19390  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Elk Grove Gary Grunwald (916)478-2236   ggrunwald@elkgrovecity.org
Design (PS&E) Phase
City of Elk Grove Gary Grunwald (916)478-2236   ggrunwald@elkgrovecity.org
Right of Way Phase
City of Elk Grove Gary Grunwald (916)478-2236   ggrunwald@elkgrovecity.org
Construction Phase
City of Elk Grove Gary Grunwald (916)478-2236   ggrunwald@elkgrovecity.org
 
Corridor System Management Plan
City of Elk Grove Gary Grunwald (916)478-2236   ggrunwald@elkgrovecity.org
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$5,000 $0 $5,000
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$3,981 $0 $3,981
Non Budgeted ETC
$0 $0 $0
 
Total**** $8,981 $0 $8,981

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$250 $0 $250 $250
Design(PS&E)
$1,700 $0 $1,700 $1,700
Right of Way
$135 $0 $135 $135
Construction
$6,896 $0 $6,896 $7,157
 
Total* $8,981 $0 $8,981 $9,242

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/2006 

12/09/2009 
 

 
07/01/2006 

12/09/2009 
100  03/01/2005 

12/30/2010 
16 

-13 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2010 

07/01/2012 
 

 
01/01/2010 

07/01/2012 
100  12/30/2010 

08/01/2012 
-12 

-1 
Begin Right of Way Phase

End Right of Way Phase
06/01/2010 

06/01/2012 
 

 
06/01/2010 

06/01/2012 
100  03/01/2011 

07/03/2012 
-9 

-1 
Begin Construction Phase

End Construction Phase
05/01/2013 

07/01/2014 
08/11/2016 

 
05/01/2013 

07/01/2014 
100  08/01/2013 

10/16/2015 
-3 

-16 
Begin Closeout Phase

End Closeout Phase
08/01/2014 

12/01/2014 
 

 
08/01/2014 

12/01/2014 
100  10/16/2015 

09/30/2017 
-15 

-34 
Corridor System Management Plan
Adoption Date 06/03/2009    06/03/2009  06/03/2009 
Implementation Date 06/30/2009    06/30/2009  06/30/2009 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 630 650
Lane Miles Added (HOV) 0
Lane Miles Added (Mixed) 0
Peak Period Time Savings (minutes) 25750 19390

Bond Funding Cost
Adopted:
$5,000,000
Current Approved:
$5,000,000
Actual Expenditures:
$5,000,000

 

Status as of December 31, 2023.