Atwater-Merced Expressway Phase 1A |
Description: Near Atwater, from 1.0 mile south of Buhach Road to 0.1 mile north of Buhach Road. Widen to 6-lane freeway, including demolition of Buhach Road interchange, and construct new interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced |
City | Merced |
Zip Code | 95341 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
County/State Route | Merced 99 |
Postmile Begin/End | 19.3 20.9 |
County/State Route | Merced 99 |
Postmile Begin/End | 19.5 20.7 |
County/State Route | Merced 99 |
Postmile Begin/End | 19.5 20.7 |
County/State Route | Merced 99 |
Postmile Begin/End | 19.5 20.7 |
County/State Route | Merced 99 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 413 | 413 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 32661 | 32,857 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Merced County Association of Governments | Stacie Dabbs | (209)723-3153 | stacie.dabbs@mcagov.org | |
Design (PS&E) Phase |
Merced County Association of Governments | Stacie Dabbs | (209)723-3153 | stacie.dabbs@mcagov.org | |
Right of Way Phase |
Merced County Association of Governments | Stacie Dabbs | (209)723-3153 | stacie.dabbs@mcagov.org | |
Construction Phase |
Merced County | Steven Rough | (209) 385-7601 | srough@co.merced.ca.us | |
Corridor System Management Plan |
Merced County | Marjie Kirn | (209)723-3153 | marjie.kirn@mcagov.org |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$52,000 | $-10,563 | $41,437 | ||||
Non-bond Funding | |||||||
State/Federal* |
$11,882 | $0 | $11,882 | ||||
Local** |
$7,477 | $0 | $7,477 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $71,359 | $-10,563 | $60,796 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,277 | $0 | $3,277 | $3,614 | |||
Design(PS&E) |
$3,700 | $0 | $3,700 | $3,705 | |||
Right of Way |
$12,382 | $0 | $12,382 | $12,378 | |||
Construction |
$52,000 | $-10,563 | $41,437 | $41,436 | |||
Total* | $71,359 | $-10,563 | $60,796 | $61,134 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2005 12/08/2009 |
|
05/01/2005 12/08/2009 |
100 | 07/01/2002 12/08/2009 |
34 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2010 09/12/2012 |
|
07/01/2010 01/03/2013 |
100 | 07/01/2010 01/03/2013 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/01/2010 06/12/2012 |
|
07/01/2010 12/18/2012 |
100 | 07/01/2010 12/18/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/17/2012 12/27/2014 |
08/11/2016 |
06/12/2013 02/01/2016 |
100 | 06/19/2013 11/02/2016 |
0 -9 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2015 04/01/2015 |
|
08/01/2016 12/01/2016 |
100 | 04/04/2017 09/23/2020 |
-8 -46 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/08/2008 | 10/08/2008 | 0 | 0 | |||
Implementation Date | 12/18/2012 | 12/18/2012 | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 413 | 413 |
Lane Miles Added (HOV) | 0 | |
Lane Miles Added (Mixed) | 0 | |
Peak Period Time Savings (minutes) | 32661 | 32,857 |
Bond Funding Cost | |
---|---|
Adopted: |
$52,000,000 |
Current Approved: |
$46,521,000 |
Actual Expenditures: |
$41,318 |
Status as of December 31, 2023.