State Route 99/Elkhorn Boulevard Improvement Project |
Description: In the city of Sacramento, at the Elkhorn Boulevard interchange. Widen northbound off ramp and signalize northbound ramp intersection.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Sacramento |
Zip Code | 95835 |
Senate District |
06 |
Assembly District | 07 |
Congressional District | 06 |
Caltrans District |
03 |
County/State Route | Sacramento 99 |
Postmile Begin/End | 33 34 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 145 | |
Peak Period Time Savings (minutes) | 1600 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Sacramento | Nader Kamal | (916)808-7035 | nkamal@cityofsacramento.org | |
Design (PS&E) Phase |
City of Sacramento | Nader Kamal | (916)808-7035 | nkamal@cityofsacramento.org | |
Right of Way Phase |
City of Sacramento | Nader Kamal | (916)808-7035 | nkamal@cityofsacramento.org | |
Construction Phase |
City of Sacramento | Marc Lee | (916)808-7481 | mlee@cityofsacramento.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$1,500 | $-392 | $1,108 | ||||
Non-bond Funding | |||||||
Local** |
$900 | $-78 | $822 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $2,400 | $-470 | $1,930 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$200 | $0 | $200 | $89 | |||
Design(PS&E) |
$400 | $0 | $400 | $431 | |||
Right of Way |
$0 | $0 | $0 | $0 | |||
Construction |
$1,800 | $-470 | $1,330 | $1,658 | |||
Total* | $2,400 | $-470 | $1,930 | $2,178 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
02/23/2011 04/01/2012 |
|
02/23/2011 04/01/2012 |
100 | 02/23/2011 04/20/2012 |
0 -1 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
04/01/2012 12/14/2012 |
|
04/01/2012 12/14/2012 |
100 | 04/23/2012 07/29/2013 |
-1 -8 |
|
Begin Right of Way Phase
End Right of Way Phase |
07/19/2012 09/06/2012 |
|
07/19/2012 09/06/2012 |
100 | 07/19/2012 09/06/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
07/01/2013 12/01/2013 |
|
07/01/2013 12/01/2013 |
100 | 07/30/2013 07/30/2015 |
-1 -20 |
|
Begin Closeout Phase
End Closeout Phase |
01/01/2014 12/01/2014 |
|
01/01/2014 12/01/2014 |
100 | 07/30/2015 07/30/2016 |
-19 -20 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 06/01/2009 | 06/01/2009 | 0 | 05/30/2009 | 0 | ||
Implementation Date | 06/01/2009 | 06/01/2009 | 0 | 06/30/2009 | -1 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 145 | |
Peak Period Time Savings (minutes) | 1600 |
Bond Funding Cost | |
---|---|
Adopted: |
$1,500,000 |
Current Approved: |
$1,108,000 |
Actual Expenditures: |
$1,082,000 |
Status as of December 31, 2023.