State Route 99/Elkhorn Boulevard Improvement Project

Description: In the city of Sacramento, at the Elkhorn Boulevard interchange. Widen northbound off ramp and signalize northbound ramp intersection.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Sacramento
Zip Code 95835
 
Senate District
06
Assembly District 07
Congressional District 06
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 33 34
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  145      
Peak Period Time Savings (minutes)  1600      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Sacramento Nader Kamal (916)808-7035   nkamal@cityofsacramento.org
Design (PS&E) Phase
City of Sacramento Nader Kamal (916)808-7035   nkamal@cityofsacramento.org
Right of Way Phase
City of Sacramento Nader Kamal (916)808-7035   nkamal@cityofsacramento.org
Construction Phase
City of Sacramento Marc Lee (916)808-7481   mlee@cityofsacramento.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$1,500 $-392 $1,108
Non-bond Funding
Local**
$900 $-78 $822
Non Budgeted ETC
$0 $0 $0
 
Total**** $2,400 $-470 $1,930

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$200 $0 $200 $89
Design(PS&E)
$400 $0 $400 $431
Right of Way
$0 $0 $0 $0
Construction
$1,800 $-470 $1,330 $1,658
 
Total* $2,400 $-470 $1,930 $2,178

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/23/2011 

04/01/2012 
 

 
02/23/2011 

04/01/2012 
100  02/23/2011 

04/20/2012 


-1 
Begin Design (PS&E) Phase

End Design (PS&E) Phase
04/01/2012 

12/14/2012 
 

 
04/01/2012 

12/14/2012 
100  04/23/2012 

07/29/2013 
-1 

-8 
Begin Right of Way Phase

End Right of Way Phase
07/19/2012 

09/06/2012 
 

 
07/19/2012 

09/06/2012 
100  07/19/2012 

09/06/2012 


Begin Construction Phase

End Construction Phase
07/01/2013 

12/01/2013 
 

 
07/01/2013 

12/01/2013 
100  07/30/2013 

07/30/2015 
-1 

-20 
Begin Closeout Phase

End Closeout Phase
01/01/2014 

12/01/2014 
 

 
01/01/2014 

12/01/2014 
100  07/30/2015 

07/30/2016 
-19 

-20 
Corridor System Management Plan
Adoption Date 06/01/2009    06/01/2009  05/30/2009 
Implementation Date 06/01/2009    06/01/2009  06/30/2009  -1 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 145
Peak Period Time Savings (minutes) 1600

Bond Funding Cost
Adopted:
$1,500,000
Current Approved:
$1,108,000
Actual Expenditures:
$1,082,000

 

Status as of December 31, 2023.