Pelandale Avenue Interchange

Description: In Modesto and Salida, from 0.75 mile south of Pelandale Avenue to 0.35 mile north of Pelandale Avenue. Reconstruct the SR99/Pelandale interchange and construct auxiliary lane.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Modesto
Zip Code 95356
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
 
County/State Route Stanislaus 99
Postmile Begin/End 21 22.4
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  6595    6640  
Peak Period Time Savings (minutes)  79140    79680  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Arvinder Bajwa (209)948-7988   arvinder.bajwa@dot.ca.gov
Design (PS&E) Phase
Caltrans Arvinder Bajwa (209)948-7988   arvinder.bajwa@dot.ca.gov
Right of Way Phase
Caltrans Arvinder Bajwa (209)948-7988   arvinder.bajwa@dot.ca.gov
Construction Phase
Caltrans Jim Robinson (209)942-6065   Jim.Robinson@dot.ca.gov
 
Corridor System Management Plan
Caltrans Joy Pinne (209)948-7854   joy.pinne@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$43,800 $-4,241 $39,559
Non-bond Funding
State/Federal*
$4,336 $-4,336 $0
Local**
$13,035 $550 $13,585
 
Total**** $61,171 $-8,027 $53,144

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,329 $0 $1,329 $2,736
Design(PS&E)
$3,019 $0 $3,019 $3,040
Right of Way
$13,023 $-4,336 $8,687 $4,371
Construction
$43,800 $-3,691 $40,109 $39,559
 
Total* $61,171 $-8,027 $53,144 $49,705

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/2002 

12/21/2009 
 

 
12/01/2002 

12/21/2009 
100  12/01/2002 

12/21/2009 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/21/2009 

07/18/2012 
 

 
12/21/2009 

07/18/2012 
100  12/21/2009 

07/16/2012 


Begin Right of Way Phase

End Right of Way Phase
12/21/2009 

07/02/2012 
 

 
12/21/2009 

07/02/2012 
100  12/21/2009 

07/02/2012 


Begin Construction Phase

End Construction Phase
12/12/2013 

12/01/2016 
 

 
02/25/2014 

12/01/2016 
100  03/12/2014 

06/30/2017 


-7 
Begin Closeout Phase

End Closeout Phase
12/01/2016 

12/01/2018 
 

 
12/10/2016 

12/01/2017 
100  08/01/2019 

04/20/2021 
-32 

-41 
Corridor System Management Plan
Adoption Date 04/06/2011    04/06/2011  04/06/2011 
Implementation Date 05/06/2011    05/06/2011  05/06/2011 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 6595 6640
Peak Period Time Savings (minutes) 79140 79680

Bond Funding Cost
Adopted:
$43,800,000
Current Approved:
$39,559,000
Actual Expenditures:
$39,559,000

 

Status as of December 31, 2023.