Pelandale Avenue Interchange |
Description: In Modesto and Salida, from 0.75 mile south of Pelandale Avenue to 0.35 mile north of Pelandale Avenue. Reconstruct the SR99/Pelandale interchange and construct auxiliary lane.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Stanislaus |
City | Modesto |
Zip Code | 95356 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
10 |
County/State Route | Stanislaus 99 |
Postmile Begin/End | 21 22.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 6595 | 6640 |
Peak Period Time Savings (minutes) | 79140 | 79680 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Arvinder Bajwa | (209)948-7988 | arvinder.bajwa@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Arvinder Bajwa | (209)948-7988 | arvinder.bajwa@dot.ca.gov | |
Right of Way Phase |
Caltrans | Arvinder Bajwa | (209)948-7988 | arvinder.bajwa@dot.ca.gov | |
Construction Phase |
Caltrans | Jim Robinson | (209)942-6065 | Jim.Robinson@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Joy Pinne | (209)948-7854 | joy.pinne@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$43,800 | $-4,241 | $39,559 | ||||
Non-bond Funding | |||||||
State/Federal* |
$4,336 | $-4,336 | $0 | ||||
Local** |
$13,035 | $550 | $13,585 | ||||
Total**** | $61,171 | $-8,027 | $53,144 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,329 | $0 | $1,329 | $2,736 | |||
Design(PS&E) |
$3,019 | $0 | $3,019 | $3,040 | |||
Right of Way |
$13,023 | $-4,336 | $8,687 | $4,371 | |||
Construction |
$43,800 | $-3,691 | $40,109 | $39,559 | |||
Total* | $61,171 | $-8,027 | $53,144 | $49,705 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
12/01/2002 12/21/2009 |
|
12/01/2002 12/21/2009 |
100 | 12/01/2002 12/21/2009 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/21/2009 07/18/2012 |
|
12/21/2009 07/18/2012 |
100 | 12/21/2009 07/16/2012 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/21/2009 07/02/2012 |
|
12/21/2009 07/02/2012 |
100 | 12/21/2009 07/02/2012 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
12/12/2013 12/01/2016 |
|
02/25/2014 12/01/2016 |
100 | 03/12/2014 06/30/2017 |
0 -7 |
|
Begin Closeout Phase
End Closeout Phase |
12/01/2016 12/01/2018 |
|
12/10/2016 12/01/2017 |
100 | 08/01/2019 04/20/2021 |
-32 -41 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 04/06/2011 | 04/06/2011 | 0 | 04/06/2011 | 0 | ||
Implementation Date | 05/06/2011 | 05/06/2011 | 0 | 05/06/2011 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 6595 | 6640 |
Peak Period Time Savings (minutes) | 79140 | 79680 |
Bond Funding Cost | |
---|---|
Adopted: |
$43,800,000 |
Current Approved: |
$39,559,000 |
Actual Expenditures: |
$39,559,000 |
Status as of December 31, 2023.