Cartmill Interchange

Description: In and near the city of Tulare, from 0.7 mile south of Cartmill Avenue to 0.6 mile north of Cartmill Avenue. Modify interchange.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City
Zip Code 93274
 
Senate District

Assembly District
Congressional District
 
Caltrans District
06
 
 
County/State Route Tulare 99
Postmile Begin/End 31.2 32.5
Project Benefits
 Benefit Baseline Actual
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Tulare, City of Michael Miller (559)684-1745   mmiller@ci.tulare.ca.us
Design (PS&E) Phase
Tulare, City of Michael Miller (559)684-1745   mmiller@ci.tulare.ca.us
Right of Way Phase
Tulare, City of Michael Miller (559)684-1745   mmiller@ci.tulare.ca.us
Construction Phase
Tulare, City of Nick Bartsch (559)684-4209   nbartsch@ci.tulare.ca.us
 
Corridor System Management Plan
City of Tulare Mike Whitlock (559)684-4210   mwhitlock@ci.tulare.ca.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$7,000 $0 $7,000
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$29,050 $0 $29,050
 
Total**** $36,050 $0 $36,050

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$1,050 $0 $1,050 $1,359
Design(PS&E)
$2,519 $0 $2,519 $3,116
Right of Way
$4,300 $0 $4,300 $4,801
Construction
$28,181 $0 $28,181 $28,490
 
Total* $36,050 $0 $36,050 $37,766

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
11/02/2009 

10/16/2012 
 

 
03/20/2008 

10/16/2012 
100  03/20/2008 

10/16/2012 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/30/2011 

01/15/2014 
 

 
10/21/2012 

01/15/2014 
100  10/21/2012 

01/15/2014 


Begin Right of Way Phase

End Right of Way Phase
09/02/2011 

04/18/2013 
 

 
10/21/2012 

04/18/2013 
100  10/21/2012 

04/18/2013 


Begin Construction Phase

End Construction Phase
04/01/2014 

03/01/2015 
 

 
06/03/2014 

06/07/2016 
100  06/03/2014 

06/07/2016 


Begin Closeout Phase

End Closeout Phase
04/01/2015 

07/01/2015 
 

 
06/08/2016 

07/01/2018 
100  06/08/2016 

07/01/2018 


Corridor System Management Plan
Adoption Date 10/31/2007    10/31/2007  10/12/2008  -12 
Implementation Date 11/01/2008    11/01/2008  11/12/2008 
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual

Bond Funding Cost
Adopted:
$7,000,000
Current Approved:
$7,000,000
Actual Expenditures:
$7,000,000

 

Status as of December 31, 2023.