Cartmill Interchange |
Description: In and near the city of Tulare, from 0.7 mile south of Cartmill Avenue to 0.6 mile north of Cartmill Avenue. Modify interchange.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | |
Zip Code | 93274 |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
06 |
County/State Route | Tulare 99 |
Postmile Begin/End | 31.2 32.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Tulare, City of | Michael Miller | (559)684-1745 | mmiller@ci.tulare.ca.us | |
Design (PS&E) Phase |
Tulare, City of | Michael Miller | (559)684-1745 | mmiller@ci.tulare.ca.us | |
Right of Way Phase |
Tulare, City of | Michael Miller | (559)684-1745 | mmiller@ci.tulare.ca.us | |
Construction Phase |
Tulare, City of | Nick Bartsch | (559)684-4209 | nbartsch@ci.tulare.ca.us | |
Corridor System Management Plan |
City of Tulare | Mike Whitlock | (559)684-4210 | mwhitlock@ci.tulare.ca.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$7,000 | $0 | $7,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$29,050 | $0 | $29,050 | ||||
Total**** | $36,050 | $0 | $36,050 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$1,050 | $0 | $1,050 | $1,359 | |||
Design(PS&E) |
$2,519 | $0 | $2,519 | $3,116 | |||
Right of Way |
$4,300 | $0 | $4,300 | $4,801 | |||
Construction |
$28,181 | $0 | $28,181 | $28,490 | |||
Total* | $36,050 | $0 | $36,050 | $37,766 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
11/02/2009 10/16/2012 |
|
03/20/2008 10/16/2012 |
100 | 03/20/2008 10/16/2012 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/30/2011 01/15/2014 |
|
10/21/2012 01/15/2014 |
100 | 10/21/2012 01/15/2014 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/02/2011 04/18/2013 |
|
10/21/2012 04/18/2013 |
100 | 10/21/2012 04/18/2013 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
04/01/2014 03/01/2015 |
|
06/03/2014 06/07/2016 |
100 | 06/03/2014 06/07/2016 |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
04/01/2015 07/01/2015 |
|
06/08/2016 07/01/2018 |
100 | 06/08/2016 07/01/2018 |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 10/31/2007 | 10/31/2007 | 0 | 10/12/2008 | -12 | ||
Implementation Date | 11/01/2008 | 11/01/2008 | 0 | 11/12/2008 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bond Funding Cost | |
---|---|
Adopted: |
$7,000,000 |
Current Approved: |
$7,000,000 |
Actual Expenditures: |
$7,000,000 |
Status as of December 31, 2023.