West Elkhorn Auxiliary Lanes

Description: In Sacramento County in Sacramento from I-5 Connector to West Elkhorn Boulevard OC, construct auxiliary lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City
Zip Code
 
Senate District
06
Assembly District 07
Congressional District 06
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 32.5 33.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)      262  
Peak Period Time Savings (minutes)      250  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Nadarajah Suthahar (930) 741-4008   sutha.suthahar@dot.ca.gov
Design (PS&E) Phase
Caltrans Nadarajah Suthahar (930) 741-4008   sutha.suthahar@dot.ca.gov
Right of Way Phase
Caltrans Nadarajah Suthahar (930) 741-4008   sutha.suthahar@dot.ca.gov
Construction Phase
Caltrans Nadarajah Suthahar (930) 741-4008   sutha.suthahar@dot.ca.gov
 
Corridor System Management Plan
Caltrans Nadarajah Suthahar (930) 741-4008   sutha.suthahar@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$5,295 $0 $5,295
TCIF
$0 $900 $900
Non-bond Funding
Local**
$0 $900 $900
 
Total**** $5,295 $1,800 $7,095

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$170 $0 $170 $169
Design(PS&E)
$600 $0 $600 $579
Right of Way
$25 $0 $25 $8
Construction
$4,500 $1,800 $6,300 $4,616
 
Total* $5,295 $1,800 $7,095 $5,372

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
06/30/2016 

02/23/2017 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
02/23/2017 

10/16/2017 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
02/23/2017 

07/28/2017 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
12/01/2018 

12/01/2018 
 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/01/2019 

09/01/2023 
 

 


Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 262
Peak Period Time Savings (minutes) 250

Bond Funding Cost
Adopted:
$0
Current Approved:
$5,295,000
Actual Expenditures:
$3,639,000

 

Status as of December 31, 2023.