Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Madera 99 Widening |
Description: In the city of Madera, from Avenue 12 to Avenue 17. Widen from 4 to 6 lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera |
City | Madera |
Zip Code | |
Senate District |
12 |
Assembly District | 29 |
Congressional District | 19 |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Department of Transportation | Anand Kapoor | (559) 243-3588 | anand.kapoor@dot.ca.gov | |
Design (PS&E) Phase |
Department of Transportation | Anand Kapoor | (559) 243-3588 | anand.kapoor@dot.ca.gov | |
Right of Way Phase |
Department of Transportation | Anand Kapoor | (559) 243-3588 | anand.kapoor@dot.ca.gov | |
Construction Phase |
Department of Transportation | Anand Kapoor | (559) 243-3588 | anand.kapoor@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$13,720 | $1,250 | $14,970 | ||||
Non-bond Funding | |||||||
State/Federal* |
$72,747 | $0 | $72,747 | ||||
Local** |
$4,850 | $0 | $4,850 | ||||
Total**** | $91,317 | $1,250 | $92,567 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$2,250 | $0 | $2,250 | $2,250 | |||
Design(PS&E) |
$5,195 | $0 | $5,195 | $5,854 | |||
Right of Way |
$450 | $0 | $450 | $424 | |||
Construction |
$83,422 | $1,250 | $84,672 | $75,126 | |||
Total* | $91,317 | $1,250 | $92,567 | $74,353 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
01/07/2013 08/14/2015 |
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
09/01/2015 07/05/2018 |
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
09/01/2015 06/16/2018 |
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2019 08/15/2021 |
|
|
0 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
08/15/2021 08/15/2025 |
|
|
0 | |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.