Livingston Widening Northbound |
Description: In Livingston, from 0.8 mile south of Hammatt Avenue to Merced/Stanislaus county line. Widen freeway from two lanes to three lanes in the northbound direction only.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced |
City | Livingston |
Zip Code | 95334 |
Senate District |
12 |
Assembly District | 17 |
Congressional District | 18 |
Caltrans District |
10 |
County/State Route | Merced 99 |
Postmile Begin/End | 28.2 R 37.3 |
County/State Route | Merced 99 |
Postmile Begin/End | 28.2 R 37.3 |
County/State Route | Merced 99 |
Postmile Begin/End | 28.2 R 37.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 8 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Dina EL-Nakhal | (209) 351-4432 | dina.el.nakhal@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Dina EL-Nakhal | (209) 351-4432 | dina.el.nakhal@dot.ca.gov | |
Right of Way Phase |
Caltrans | Dina EL-Nakhal | (209) 351-4432 | dina.el.nakhal@dot.ca.gov | |
Construction Phase |
Caltrans | Dina EL-Nakhal | (209) 351-4432 | dina.el.nakhal@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$8,716 | $0 | $8,716 | ||||
TCIF |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$8,370 | $28,864 | $37,234 | ||||
Total**** | $17,086 | $28,864 | $45,950 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$800 | $0 | $800 | $0 | |||
Design(PS&E) |
$2,050 | $0 | $2,050 | $2,406 | |||
Right of Way |
$20 | $0 | $20 | $32 | |||
Construction |
$14,216 | $28,864 | $43,080 | $38,973 | |||
Total* | $17,086 | $28,864 | $45,950 | $40,167 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
06/02/2014 |
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
08/01/2014 01/12/2018 |
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
08/12/2014 12/12/2017 |
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
08/03/2020 04/15/2022 |
|
|
0 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/07/2023 05/07/2025 |
|
|
0 | |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 8 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.