Plainsburg-Arboleda Mitigation |
Description: Mitigation construction on State Route 99 in Merced County about 10 miles north of Chowchilla at the Le Grand Road overcrossing and the Plainsburg Road overcrossing.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Merced |
City | Merced |
Zip Code | 95340 |
Senate District |
12 |
Assembly District | 21 |
Congressional District | 16 |
Caltrans District |
10 |
County/State Route | Merced 99 |
Postmile Begin/End | 3.4 6.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Thienan Nguyentan | (209) 986-5356 | Thienan.Nguyentan@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Michael Cook | (209) 470-2909 | mike.cook@dot.ca.gov | |
Right of Way Phase |
Caltrans | Michael Cook | (209) 470-2909 | mike.cook@dot.ca.gov | |
Construction Phase |
Caltrans | Michael Cook | (209) 470-2909 | mike.cook@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Michael Cook | (209) 470-2909 | mike.cook@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$1,478 | $3,356 | $4,834 | ||||
Non-bond Funding | |||||||
Non Budgeted ETC |
$3,028 | $-3,028 | $0 | ||||
Total**** | $4,506 | $328 | $4,834 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$330 | $-255 | $75 | $73 | |||
Design(PS&E) |
$1,121 | $340 | $1,461 | $388 | |||
Right of Way |
$27 | $3 | $30 | $1 | |||
Construction |
$3,028 | $240 | $3,268 | $0 | |||
Total* | $4,506 | $328 | $4,834 | $462 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
08/15/2020 02/15/2021 |
|
08/15/2020 02/15/2021 |
100 | 09/04/2020 02/26/2021 |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/16/2021 01/16/2023 |
|
06/16/2021 01/16/2023 |
0 | 07/06/2021 |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
12/16/2022 |
|
12/16/2022 |
0 | 07/19/2021 |
0 0 |
|
Begin Construction Phase
End Construction Phase |
06/22/2023 05/22/2029 |
|
06/22/2023 05/22/2029 |
0 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
07/22/2031 04/22/2033 |
|
07/22/2031 04/22/2033 |
0 | |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.