South Madera 6 Lane

Description: Near the city of Madera, from 0.7 mile north of Avenue 7 to Avenue 12.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93637
 
Senate District
12
Assembly District 05
Congressional District 16
 
Caltrans District
06
 
 
County/State Route Madera 99
Postmile Begin/End 1.7 7.5
Project Benefits
 Benefit Baseline Actual
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Chris Gardner 5599781888   chris.gardner@dot.ca.gov
Design (PS&E) Phase
Caltrans Chris Gardner 5599781888   chris.gardner@dot.ca.gov
Right of Way Phase
Caltrans Chris Gardner 5599781888   chris.gardner@dot.ca.gov
Construction Phase
Caltrans Chris Gardner 5599781888   chris.gardner@dot.ca.gov
 
Corridor System Management Plan
Caltrans Chris Gardner 5599781888   chris.gardner@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
BOND99
$3,080 $0 $3,080
TCIF
$0 $0 $0
Non-bond Funding
State/Federal*
$9,813 $0 $9,813
 
Total**** $12,893 $0 $12,893

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$3,413 $0 $3,413 $3,824
Design(PS&E)
$9,480 $0 $9,480 $545
Right of Way
$0 $0 $0 $178
Construction
$0 $0 $0 $0
 
Total* $12,893 $0 $12,893 $4,376

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
05/01/2019 

05/01/2022 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
05/01/2022 

05/02/2024 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
05/01/2022 

05/01/2024 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
02/01/2025 

02/01/2027 
 

 
 

 
 

 


Begin Closeout Phase

End Closeout Phase
02/01/2027 

02/01/2030 
 

 
 

 
 

 


Corridor System Management Plan
Adoption Date        
Implementation Date        
????????

No map available at this time.

Project Benefits
Benefit Baseline Actual

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.