South Madera 6 Lane |
Description: Near the city of Madera, from 0.7 mile north of Avenue 7 to Avenue 12.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera |
City | Madera |
Zip Code | 93637 |
Senate District |
12 |
Assembly District | 05 |
Congressional District | 16 |
Caltrans District |
06 |
County/State Route | Madera 99 |
Postmile Begin/End | 1.7 7.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Chris Gardner | 5599781888 | chris.gardner@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Chris Gardner | 5599781888 | chris.gardner@dot.ca.gov | |
Right of Way Phase |
Caltrans | Chris Gardner | 5599781888 | chris.gardner@dot.ca.gov | |
Construction Phase |
Caltrans | Chris Gardner | 5599781888 | chris.gardner@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | Chris Gardner | 5599781888 | chris.gardner@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
BOND99 |
$3,080 | $0 | $3,080 | ||||
TCIF |
$0 | $0 | $0 | ||||
Non-bond Funding | |||||||
State/Federal* |
$9,813 | $0 | $9,813 | ||||
Total**** | $12,893 | $0 | $12,893 |
**** Totals may not add up exactly to column amounts due to rounding
# Approved is planned budget
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
||||
Environmental |
$3,413 | $0 | $3,413 | $3,824 | |||
Design(PS&E) |
$9,480 | $0 | $9,480 | $545 | |||
Right of Way |
$0 | $0 | $0 | $178 | |||
Construction |
$0 | $0 | $0 | $0 | |||
Total* | $12,893 | $0 | $12,893 | $4,376 |
* Totals may not add up exactly to column amounts due to rounding
** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.
Project Schedule Baseline Summary | |||||||
---|---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
|
Begin Environmental Phase
End Environmental Phase |
05/01/2019 05/01/2022 |
|
|
0 | |
0 0 |
|
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
05/01/2022 05/02/2024 |
|
|
0 | |
0 0 |
|
Begin Right of Way Phase
End Right of Way Phase |
05/01/2022 05/01/2024 |
|
|
0 | |
0 0 |
|
Begin Construction Phase
End Construction Phase |
02/01/2025 02/01/2027 |
|
|
0 | |
0 0 |
|
Begin Closeout Phase
End Closeout Phase |
02/01/2027 02/01/2030 |
|
|
0 | |
0 0 |
|
Corridor System Management Plan |
|||||||
Adoption Date | 0 | 0 | |||||
Implementation Date | 0 | 0 |
????????
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.