Caltrans Logo

Route 180 - Clovis Ave to Temperance Ave

Description: In and near Fresno from Clovis Ave to Temperance Ave. Construct 6-lane freeway from Clovis Ave to Fowler Av and 4-lane freeway from Fowler Ave to Temperance Ave. (TCRP #91)

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Fresno
City Fresno
Zip Code 93611
 
Senate District
14, 16
Assembly District 29
Congressional District 21
 
Caltrans District
06
 
 
County/State Route Fresno 180
Postmile Begin/End R  63.3 R  66.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3668      
Lane Miles Added (Mixed)  13    13  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Garth Fernandez (559) 243-8012   Garth_Fernandez@dot.ca.gov
Design (PS&E) Phase
Caltrans Garth Fernandez (559) 243-8012   Garth_Fernandez@dot.ca.gov
Right of Way Phase
Caltrans Garth Fernandez (559) 243-8012   Garth_Fernandez@dot.ca.gov
Construction Phase
Caltrans Garth Fernandez (559) 243-8012   Garth_Fernandez@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $60,555 $60,555
Non-bond Funding
State/Federal*
$0 $25,700 $25,700
Local**
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $86,255 $86,255

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $44 $44 $-44
Design(PS&E)
$0 $6,630 $6,630 $6,870 $7,064 $-434
Right of Way
$0 $11,631 $11,631 $12,113 $12,832 $-1,201
Construction
$0 $67,994 $67,994 $56,751 $56,751 $11,243
 
Total* $0 $86,255 $86,255 $75,778 $76,692 $9,563

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
02/01/2000 

01/28/2004 
 

 
02/01/2000 

01/28/2004 
100  02/01/2000 

01/28/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/28/2004 

07/13/2005 
 

 
01/28/2004 

07/13/2005 
100  01/28/2004 

07/13/2005 


Begin Right of Way Phase

End Right of Way Phase
12/13/1995 

08/08/2005 
 

 
12/13/1995 

08/08/2005 
100  12/13/1995 

08/08/2005 


Begin Construction Phase

End Construction Phase
12/17/2007 

12/01/2010 
 

 
12/17/2007 

12/01/2010 
100  01/08/2008 

11/09/2010 
-1 

Begin Closeout Phase

End Closeout Phase
12/01/2010 

06/01/2012 
 

 
12/01/2010 

06/01/2012 
100  11/09/2010 

05/10/2013 


-11 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3668
Lane Miles Added (Mixed) 13 13

Bond Funding Cost
Adopted:
$54,985,000
Current Approved:
$48,738,000
Actual Expenditures:
$45,311,709

 

Status as of December 31, 2023.