Route 180 - Clovis Ave to Temperance Ave |
Description: In and near Fresno from Clovis Ave to Temperance Ave. Construct 6-lane freeway from Clovis Ave to Fowler Av and 4-lane freeway from Fowler Ave to Temperance Ave. (TCRP #91)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Fresno |
City | Fresno |
Zip Code | 93611 |
Senate District |
14, 16 |
Assembly District | 29 |
Congressional District | 21 |
Caltrans District |
06 |
County/State Route | Fresno 180 |
Postmile Begin/End | R 63.3 R 66.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3668 | |
Lane Miles Added (Mixed) | 13 | 13 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Garth Fernandez | (559) 243-8012 | Garth_Fernandez@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Garth Fernandez | (559) 243-8012 | Garth_Fernandez@dot.ca.gov | |
Right of Way Phase |
Caltrans | Garth Fernandez | (559) 243-8012 | Garth_Fernandez@dot.ca.gov | |
Construction Phase |
Caltrans | Garth Fernandez | (559) 243-8012 | Garth_Fernandez@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $60,555 | $60,555 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $25,700 | $25,700 | ||||
Local** |
$0 | $0 | $0 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $86,255 | $86,255 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $44 | $44 | $-44 | |
Design(PS&E) |
$0 | $6,630 | $6,630 | $6,870 | $7,064 | $-434 | |
Right of Way |
$0 | $11,631 | $11,631 | $12,113 | $12,832 | $-1,201 | |
Construction |
$0 | $67,994 | $67,994 | $56,751 | $56,751 | $11,243 | |
Total* | $0 | $86,255 | $86,255 | $75,778 | $76,692 | $9,563 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
02/01/2000 01/28/2004 |
|
02/01/2000 01/28/2004 |
100 | 02/01/2000 01/28/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/28/2004 07/13/2005 |
|
01/28/2004 07/13/2005 |
100 | 01/28/2004 07/13/2005 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/13/1995 08/08/2005 |
|
12/13/1995 08/08/2005 |
100 | 12/13/1995 08/08/2005 |
0 0 |
Begin Construction Phase
End Construction Phase |
12/17/2007 12/01/2010 |
|
12/17/2007 12/01/2010 |
100 | 01/08/2008 11/09/2010 |
-1 1 |
Begin Closeout Phase
End Closeout Phase |
12/01/2010 06/01/2012 |
|
12/01/2010 06/01/2012 |
100 | 11/09/2010 05/10/2013 |
1 -11 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 3668 | |
Lane Miles Added (Mixed) | 13 | 13 |
Bond Funding Cost | |
---|---|
Adopted: |
$54,985,000 |
Current Approved: |
$48,738,000 |
Actual Expenditures: |
$45,311,709 |
Status as of December 31, 2023.