Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Sutter/Yuba Route 70 Corridor Project |
Description: Near Marysville, south of Algodon Road at Motorplex Parkway and Route 70. Construct new interchange
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Yuba |
City | Marysville |
Zip Code | 95901 |
Senate District |
04 |
Assembly District | 03 |
Congressional District | 02 |
Caltrans District |
03 |
County/State Route | Yuba 70 |
Postmile Begin/End | 3 3.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | .25 | |
Peak Period Time Savings (minutes) | 15 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
Yuba County Public Works Dept | Mike G. Lee | 530-713-4652 | MGLee@co.yuba.ca.us | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$6,632 | $0 | $6,632 | ||||
IIP Augmentation |
$5,570 | $0 | $5,570 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $0 | $0 | ||||
Local** |
$4,700 | $78 | $4,778 | ||||
Total**** | $16,902 | $78 | $16,980 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$300 | $0 | $300 | $277 | $277 | $23 | |
Design(PS&E) |
$1,200 | $0 | $1,200 | $178 | $178 | $1,022 | |
Right of Way |
$1,700 | $0 | $1,700 | $1,854 | $1,854 | $-154 | |
Construction |
$13,702 | $78 | $13,780 | $0 | $0 | $13,780 | |
Total* | $16,902 | $78 | $16,980 | $2,308 | $2,308 | $14,672 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/06/2004 |
|
12/06/2004 |
0 | 12/06/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/07/2004 12/07/2005 |
|
12/07/2004 05/08/2007 |
100 | 12/07/2004 05/08/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/07/2004 06/06/2007 |
|
12/07/2004 06/06/2007 |
100 | 12/07/2004 06/06/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
02/01/2008 11/16/2009 |
|
02/01/2008 11/16/2009 |
100 | 02/01/2008 09/11/2009 |
0 2 |
Begin Closeout Phase
End Closeout Phase |
11/17/2009 12/17/2009 |
|
11/17/2009 12/17/2009 |
50 | 09/11/2009 10/15/2009 |
2 2 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | .25 | |
Peak Period Time Savings (minutes) | 15 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$16,980,000 |
Actual Expenditures: |
$16,980,000 |
Status as of December 31, 2023.