Caltrans Logo

Sutter/Yuba Route 70 Corridor Project

Description: Near Marysville, south of Algodon Road at Motorplex Parkway and Route 70. Construct new interchange

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yuba
City Marysville
Zip Code 95901
 
Senate District
04
Assembly District 03
Congressional District 02
 
Caltrans District
03
 
 
County/State Route Yuba 70
Postmile Begin/End 3 3.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  .25      
Peak Period Time Savings (minutes)      15  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
Yuba County Public Works Dept Mike G. Lee 530-713-4652   MGLee@co.yuba.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$6,632 $0 $6,632
IIP Augmentation
$5,570 $0 $5,570
Non-bond Funding
State/Federal*
$0 $0 $0
Local**
$4,700 $78 $4,778
 
Total**** $16,902 $78 $16,980

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$300 $0 $300 $277 $277 $23
Design(PS&E)
$1,200 $0 $1,200 $178 $178 $1,022
Right of Way
$1,700 $0 $1,700 $1,854 $1,854 $-154
Construction
$13,702 $78 $13,780 $0 $0 $13,780
 
Total* $16,902 $78 $16,980 $2,308 $2,308 $14,672

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

12/06/2004 
 

 
 

12/06/2004 
 

12/06/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/07/2004 

12/07/2005 
 

 
12/07/2004 

05/08/2007 
100  12/07/2004 

05/08/2007 


Begin Right of Way Phase

End Right of Way Phase
12/07/2004 

06/06/2007 
 

 
12/07/2004 

06/06/2007 
100  12/07/2004 

06/06/2007 


Begin Construction Phase

End Construction Phase
02/01/2008 

11/16/2009 
 

 
02/01/2008 

11/16/2009 
100  02/01/2008 

09/11/2009 


Begin Closeout Phase

End Closeout Phase
11/17/2009 

12/17/2009 
 

 
11/17/2009 

12/17/2009 
50  09/11/2009 

10/15/2009 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) .25
Peak Period Time Savings (minutes) 15

Bond Funding Cost
Adopted:
$0
Current Approved:
$16,980,000
Actual Expenditures:
$16,980,000

 

Status as of December 31, 2023.