Brawley Bypass - Stage 2 |
Description: In Imperial County in and near Brawley - construct four-lane expressway
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Imperial |
City | Brawley |
Zip Code | 92227 |
Senate District |
40 |
Assembly District | 80 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | Imperial 78 |
Postmile Begin/End | R 9.2 R 12.1 |
County/State Route | Imperial 86 |
Postmile Begin/End | R 23.8 R 24.3 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 3.1 | |
Peak Period Time Savings (minutes) | 30 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Right of Way Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Construction Phase |
Caltrans | Sam Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov | |
Corridor System Management Plan |
Caltrans | San Amen | (619) 718-7835 | Sam_Amen@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $45,340 | $45,340 | ||||
IIP Augmentation |
$0 | $45,972 | $45,972 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $23,824 | $23,824 | ||||
Local** |
$0 | $3,644 | $3,644 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $118,781 | $118,781 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $5,967 | $5,967 | $2,192 | $2,192 | $3,774 | |
Design(PS&E) |
$0 | $10,123 | $10,123 | $9,954 | $9,954 | $169 | |
Right of Way |
$0 | $22,786 | $22,786 | $26,740 | $26,740 | $-3,954 | |
Construction |
$0 | $79,906 | $79,906 | $92,485 | $92,485 | $-12,579 | |
Total* | $0 | $118,781 | $118,781 | $131,370 | $131,370 | $-12,589 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
02/19/2003 |
100 | 02/19/2003 02/19/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
06/15/2007 |
100 | 06/15/2007 12/07/2005 |
0 19 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
12/15/2005 05/24/2007 |
99 | 05/24/2007 11/30/2010 |
-17 -43 |
Begin Construction Phase
End Construction Phase |
|
|
11/30/2010 12/10/2014 |
0 | 12/10/2014 12/10/2012 |
-49 24 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/10/2012 06/24/2016 |
100 | 06/24/2016 06/24/2016 |
-43 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 3.1 | |
Peak Period Time Savings (minutes) | 30 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$105,470,110 |
Actual Expenditures: |
$89,300,126 |
Status as of December 31, 2023.