Brawley Bypass - Stage 2

Description: In Imperial County in and near Brawley - construct four-lane expressway

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Imperial
City Brawley
Zip Code 92227
 
Senate District
40
Assembly District 80
Congressional District 51
 
Caltrans District
11
 
 
County/State Route Imperial 78
Postmile Begin/End R  9.2 R  12.1
 
County/State Route Imperial 86
Postmile Begin/End R  23.8 R  24.3
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  3.1      
Peak Period Time Savings (minutes)  30      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Design (PS&E) Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Right of Way Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Construction Phase
Caltrans Sam Amen (619) 718-7835   Sam_Amen@dot.ca.gov
 
Corridor System Management Plan
Caltrans San Amen (619) 718-7835   Sam_Amen@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $45,340 $45,340
IIP Augmentation
$0 $45,972 $45,972
Non-bond Funding
State/Federal*
$0 $23,824 $23,824
Local**
$0 $3,644 $3,644
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $118,781 $118,781

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $5,967 $5,967 $2,192 $2,192 $3,774
Design(PS&E)
$0 $10,123 $10,123 $9,954 $9,954 $169
Right of Way
$0 $22,786 $22,786 $26,740 $26,740 $-3,954
Construction
$0 $79,906 $79,906 $92,485 $92,485 $-12,579
 
Total* $0 $118,781 $118,781 $131,370 $131,370 $-12,589

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

02/19/2003 
100  02/19/2003 

02/19/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

06/15/2007 
100  06/15/2007 

12/07/2005 


19 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
12/15/2005 

05/24/2007 
99  05/24/2007 

11/30/2010 
-17 

-43 
Begin Construction Phase

End Construction Phase
 

 
 

 
11/30/2010 

12/10/2014 
12/10/2014 

12/10/2012 
-49 

24 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/10/2012 

06/24/2016 
100  06/24/2016 

06/24/2016 
-43 

????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 3.1
Peak Period Time Savings (minutes) 30

Bond Funding Cost
Adopted:
$0
Current Approved:
$105,470,110
Actual Expenditures:
$89,300,126

 

Status as of December 31, 2023.