New Rte 52 Fwy-Rte 125 to Cuyamaca-West end |
Description: In Santee from Route 125 to Cuyamaca Street. Construct 4-lane Freeway (West End) (including FCO $ for Forester Creek Channelization).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | Santee |
Zip Code | 92071 |
Senate District |
36 |
Assembly District | 77 |
Congressional District | 52 |
Caltrans District |
11 |
County/State Route | San Diego 52 |
Postmile Begin/End | 14.1 16.3 |
County/State Route | San Diego 52 |
Postmile Begin/End | |
County/State Route | San Diego 52 |
Postmile Begin/End | |
County/State Route | San Diego 52 |
Postmile Begin/End | |
County/State Route | San Diego 52 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 13.2 | 13.2 |
Peak Period Time Savings (minutes) | 10 | 10 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Andrew Rice | (619) 688 3284 | Andrew_Rice@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Andrew Rice | (619) 688 3284 | Andrew_Rice@dot.ca.gov | |
Right of Way Phase |
Caltrans | Andrew Rice | (619) 688 3284 | Andrew_Rice@dot.ca.gov | |
Construction Phase |
Caltrans | Andrew Rice | (619) 688 3284 | Andrew_Rice@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $79,328 | $79,328 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $76,371 | $76,371 | ||||
Local** |
$0 | $42,190 | $42,190 | ||||
Total**** | $0 | $197,889 | $197,889 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $17,000 | $17,000 | $15,205 | $15,205 | $1,795 | |
Right of Way |
$0 | $100,283 | $100,283 | $91,003 | $91,003 | $9,280 | |
Construction |
$0 | $80,606 | $80,606 | $76,218 | $76,218 | $4,388 | |
Total* | $0 | $197,889 | $197,889 | $182,426 | $182,426 | $15,463 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/28/1989 |
|
07/28/1989 |
100 | 07/28/1989 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/31/2003 08/14/2007 |
|
03/31/2003 08/14/2007 |
100 | 03/31/2003 08/14/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/15/2004 06/21/2007 |
|
01/15/2004 06/21/2007 |
100 | 01/15/2004 06/21/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
11/27/2007 12/30/2011 |
|
11/27/2007 12/30/2010 |
100 | 11/27/2007 12/30/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
04/01/2011 12/31/2011 |
|
05/11/2011 06/30/2013 |
100 | 05/11/2011 01/21/2015 |
0 -19 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 13.2 | 13.2 |
Peak Period Time Savings (minutes) | 10 | 10 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$74,942,000 |
Actual Expenditures: |
$74,942,000 |
Status as of December 31, 2023.