Caltrans Logo

SR 70 Passing Lanes

Description: From 0.7 mile south of East Gridley Rd to 0.6 mile north of Cox Lane. Construct passing lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Gridley
Zip Code 95948
 
Senate District
04
Assembly District 02, 03
Congressional District 04
 
Caltrans District
03
 
 
County/State Route Butte 70
Postmile Begin/End 3.3 6.8
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  101    240  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans John Holder (530)741-5448   John_Holder@dot.ca.gov
Design (PS&E) Phase
Caltrans John Holder (530)741-5448   John_Holder@dot.ca.gov
Right of Way Phase
Caltrans John Holder (530)741-5448   John_Holder@dot.ca.gov
Construction Phase
Caltrans John Holder (530)741-5448   John_Holder@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
IIP Augmentation
$0 $2,166 $2,166
Non-bond Funding
State/Federal*
$0 $17,234 $17,234
 
Total**** $0 $19,400 $19,400

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $216 $216 $216 $216 $-0
Design(PS&E)
$0 $1,950 $1,950 $2,132 $2,132 $-182
Right of Way
$0 $3,434 $3,434 $2,635 $3,150 $284
Construction
$0 $13,800 $13,800 $9,575 $9,961 $3,839
 
Total* $0 $19,400 $19,400 $14,559 $15,460 $3,940

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
04/01/2006 

03/03/2008 
 

 
04/01/2006 

03/03/2008 
04/01/2006 

03/03/2008 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/03/2008 

10/15/2010 
 

 
03/03/2008 

09/03/2010 
03/03/2008 

09/03/2010 


Begin Right of Way Phase

End Right of Way Phase
05/23/2008 

10/15/2010 
 

 
05/23/2008 

08/06/2010 
05/23/2008 

08/16/2010 


Begin Construction Phase

End Construction Phase
03/01/2011 

06/01/2013 
 

 
03/03/2011 

07/19/2013 
100  03/03/2011 

07/19/2013 


Begin Closeout Phase

End Closeout Phase
06/01/2013 

06/01/2015 
 

 
07/19/2013 

11/15/2016 
50  07/19/2013 

11/15/2016 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 101 240

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.