SR 70 Passing Lanes |
Description: From 0.7 mile south of East Gridley Rd to 0.6 mile north of Cox Lane. Construct passing lanes.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Butte |
City | Gridley |
Zip Code | 95948 |
Senate District |
04 |
Assembly District | 02, 03 |
Congressional District | 04 |
Caltrans District |
03 |
County/State Route | Butte 70 |
Postmile Begin/End | 3.3 6.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 101 | 240 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | John Holder | (530)741-5448 | John_Holder@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | John Holder | (530)741-5448 | John_Holder@dot.ca.gov | |
Right of Way Phase |
Caltrans | John Holder | (530)741-5448 | John_Holder@dot.ca.gov | |
Construction Phase |
Caltrans | John Holder | (530)741-5448 | John_Holder@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
IIP Augmentation |
$0 | $2,166 | $2,166 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $17,234 | $17,234 | ||||
Total**** | $0 | $19,400 | $19,400 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $216 | $216 | $216 | $216 | $-0 | |
Design(PS&E) |
$0 | $1,950 | $1,950 | $2,132 | $2,132 | $-182 | |
Right of Way |
$0 | $3,434 | $3,434 | $2,635 | $3,150 | $284 | |
Construction |
$0 | $13,800 | $13,800 | $9,575 | $9,961 | $3,839 | |
Total* | $0 | $19,400 | $19,400 | $14,559 | $15,460 | $3,940 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
04/01/2006 03/03/2008 |
|
04/01/2006 03/03/2008 |
0 | 04/01/2006 03/03/2008 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/03/2008 10/15/2010 |
|
03/03/2008 09/03/2010 |
0 | 03/03/2008 09/03/2010 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
05/23/2008 10/15/2010 |
|
05/23/2008 08/06/2010 |
0 | 05/23/2008 08/16/2010 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/01/2011 06/01/2013 |
|
03/03/2011 07/19/2013 |
100 | 03/03/2011 07/19/2013 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
06/01/2013 06/01/2015 |
|
07/19/2013 11/15/2016 |
50 | 07/19/2013 11/15/2016 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Daily Travel Time Savings (hours) | 101 | 240 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.