Caltrans Logo

Route 99/Sheldon Rd Interchange

Description: Route 99 at Sheldon Rd, reconstruct interchange and construct park and ride lot.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sacramento
City Elk Grove
Zip Code 95758
 
Senate District
01, 05
Assembly District 10
Congressional District 03, 05
 
Caltrans District
03
 
 
County/State Route Sacramento 99
Postmile Begin/End 14.3 15.5
Project Benefits
 Benefit Baseline Actual
Ramp Widenings  4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
City of Elk Grove Richard Shepard 916-478-2287   rshepard@elkgrovecity.org
Right of Way Phase
 
Construction Phase
City of Elk Grove Richard Shepard 916-478-2287   rshepard@elkgrovecity.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,962 $10,962
Non-bond Funding
State/Federal*
$0 $5,272 $5,272
Local**
$0 $57,127 $57,127
 
Total**** $0 $73,361 $73,361

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $0 $0 $0
Design(PS&E)
$0 $6,220 $6,220 $0 $0 $6,220
Right of Way
$0 $28,392 $28,392 $0 $0 $28,392
Construction
$0 $38,749 $38,749 $0 $0 $38,749
 
Total* $0 $73,361 $73,361 $0 $0 $73,361

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
05/01/2006 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
08/14/2007 

08/01/2005 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

01/21/2008 


Begin Construction Phase

End Construction Phase
 

 
 

 
01/08/2008 

12/01/2009 
100  03/11/2010 

03/01/2011 
-26 

-15 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/01/2009 

12/01/2011 
12/31/2017 

12/31/2017 
-98 

-74 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Ramp Widenings 4

Bond Funding Cost
Adopted:
$0
Current Approved:
$10,962,000
Actual Expenditures:
$10,962,000

 

Status as of December 31, 2023.