Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Route 99/Sheldon Rd Interchange |
Description: Route 99 at Sheldon Rd, reconstruct interchange and construct park and ride lot.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sacramento |
City | Elk Grove |
Zip Code | 95758 |
Senate District |
01, 05 |
Assembly District | 10 |
Congressional District | 03, 05 |
Caltrans District |
03 |
County/State Route | Sacramento 99 |
Postmile Begin/End | 14.3 15.5 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp Widenings | 4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
City of Elk Grove | Richard Shepard | 916-478-2287 | rshepard@elkgrovecity.org | |
Right of Way Phase |
|||||
Construction Phase |
City of Elk Grove | Richard Shepard | 916-478-2287 | rshepard@elkgrovecity.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,962 | $10,962 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $5,272 | $5,272 | ||||
Local** |
$0 | $57,127 | $57,127 | ||||
Total**** | $0 | $73,361 | $73,361 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $6,220 | $6,220 | $0 | $0 | $6,220 | |
Right of Way |
$0 | $28,392 | $28,392 | $0 | $0 | $28,392 | |
Construction |
$0 | $38,749 | $38,749 | $0 | $0 | $38,749 | |
Total* | $0 | $73,361 | $73,361 | $0 | $0 | $73,361 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | 05/01/2006 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | 08/14/2007 08/01/2005 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | 01/21/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
01/08/2008 12/01/2009 |
100 | 03/11/2010 03/01/2011 |
-26 -15 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/01/2009 12/01/2011 |
0 | 12/31/2017 12/31/2017 |
-98 -74 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Ramp Widenings | 4 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$10,962,000 |
Actual Expenditures: |
$10,962,000 |
Status as of December 31, 2023.