Dana to Downtown Phase A & B |
Description: Redding, Route 5 from East St. to 0.5 km east Sac. River Br. & from .5 S to .2 km N of Route 5/44 Sep. Replace Bridge, construct Auditorium Dr, OC E/B & W/B aux lanes, widen Continental St. UC.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Shasta |
City | Redding |
Zip Code | 96019 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
02 |
County/State Route | Shasta 44 |
Postmile Begin/End | L 0.3 L 1.8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | 1.3 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Eric Orr | 530-225-3466 | eric.orr@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Eric Orr | 530-225-3466 | eric.orr@dot.ca.gov | |
Right of Way Phase |
Caltrans | Eric Orr | 530-225-3466 | eric.orr@dot.ca.gov | |
Construction Phase |
Caltrans | Eric Orr | 530-225-3466 | eric.orr@dot.ca.gov | |
Corridor System Management Plan |
Calrans | Scott White | 530-229-0518 | scott_white@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $38,294 | $38,294 | ||||
IIP Augmentation |
$0 | $32,923 | $32,923 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $7,726 | $7,726 | ||||
Local** |
$0 | $0 | $0 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $78,943 | $78,943 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $1,228 | $1,228 | $2,272 | $2,272 | $-1,044 | |
Design(PS&E) |
$0 | $4,458 | $4,458 | $5,999 | $5,999 | $-1,541 | |
Right of Way |
$0 | $540 | $540 | $495 | $495 | $45 | |
Construction |
$0 | $72,717 | $72,717 | $71,129 | $71,453 | $1,264 | |
Total* | $0 | $78,943 | $78,943 | $79,895 | $80,218 | $-1,275 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/01/1998 06/17/2003 |
|
12/01/1998 06/17/2003 |
100 | 12/01/1998 06/17/2003 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/18/2003 09/07/2007 |
|
06/18/2003 09/07/2007 |
100 | 06/18/2003 09/07/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
06/18/2003 06/29/2006 |
|
06/18/2003 06/29/2006 |
100 | 06/18/2003 06/29/2006 |
0 0 |
Begin Construction Phase
End Construction Phase |
03/14/2008 06/07/2012 |
|
03/14/2008 06/07/2012 |
100 | 03/10/2008 05/20/2011 |
0 13 |
Begin Closeout Phase
End Closeout Phase |
06/08/2012 06/08/2013 |
|
06/08/2012 06/08/2013 |
100 | 05/21/2011 05/31/2012 |
13 12 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 2 | |
Lane Miles Added (Mixed) | 1.3 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$71,217,000 |
Actual Expenditures: |
$69,751,000 |
Status as of December 31, 2023.