Dana to Downtown Phase A & B

Description: Redding, Route 5 from East St. to 0.5 km east Sac. River Br. & from .5 S to .2 km N of Route 5/44 Sep. Replace Bridge, construct Auditorium Dr, OC E/B & W/B aux lanes, widen Continental St. UC.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Shasta
City Redding
Zip Code 96019
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
02
 
 
County/State Route Shasta 44
Postmile Begin/End L  0.3 L  1.8
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (HOV)      2  
Lane Miles Added (Mixed)  1.3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Design (PS&E) Phase
Caltrans Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Right of Way Phase
Caltrans Eric Orr 530-225-3466   eric.orr@dot.ca.gov
Construction Phase
Caltrans Eric Orr 530-225-3466   eric.orr@dot.ca.gov
 
Corridor System Management Plan
Calrans Scott White 530-229-0518   scott_white@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $38,294 $38,294
IIP Augmentation
$0 $32,923 $32,923
Non-bond Funding
State/Federal*
$0 $7,726 $7,726
Local**
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $78,943 $78,943

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $1,228 $1,228 $2,272 $2,272 $-1,044
Design(PS&E)
$0 $4,458 $4,458 $5,999 $5,999 $-1,541
Right of Way
$0 $540 $540 $495 $495 $45
Construction
$0 $72,717 $72,717 $71,129 $71,453 $1,264
 
Total* $0 $78,943 $78,943 $79,895 $80,218 $-1,275

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
12/01/1998 

06/17/2003 
 

 
12/01/1998 

06/17/2003 
100  12/01/1998 

06/17/2003 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
06/18/2003 

09/07/2007 
 

 
06/18/2003 

09/07/2007 
100  06/18/2003 

09/07/2007 


Begin Right of Way Phase

End Right of Way Phase
06/18/2003 

06/29/2006 
 

 
06/18/2003 

06/29/2006 
100  06/18/2003 

06/29/2006 


Begin Construction Phase

End Construction Phase
03/14/2008 

06/07/2012 
 

 
03/14/2008 

06/07/2012 
100  03/10/2008 

05/20/2011 


13 
Begin Closeout Phase

End Closeout Phase
06/08/2012 

06/08/2013 
 

 
06/08/2012 

06/08/2013 
100  05/21/2011 

05/31/2012 
13 

12 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (HOV) 2
Lane Miles Added (Mixed) 1.3

Bond Funding Cost
Adopted:
$0
Current Approved:
$71,217,000
Actual Expenditures:
$69,751,000

 

Status as of December 31, 2023.