Harbor Boulevard Project

Description: In West Sacramento, on Harbor Boulevard. Widen to 6 lanes and revise ramps.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Yolo
City West Sacramento
Zip Code 95691
 
Senate District
05
Assembly District 08
Congressional District 01
 
Caltrans District
03
 
 
County/State Route Yolo 50
Postmile Begin/End 0.3 2
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  3421    3421  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Caltrans Doug Lange 530-741-4465   doug_lange@dot.ca.gov
Right of Way Phase
Caltrans Doug Lange 530-741-4465   doug_lange@dot.ca.gov
Construction Phase
Caltrans Doug Lange 530-741-4465   doug_lange@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $19,962 $19,962
Non-bond Funding
State/Federal*
$0 $8,715 $8,715
Local**
$0 $6,699 $6,699
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $35,376 $35,376

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $700 $700 $635 $635 $65
Design(PS&E)
$0 $3,200 $3,200 $4,311 $4,311 $-1,111
Right of Way
$0 $10,164 $10,164 $12,199 $12,235 $-2,071
Construction
$0 $21,312 $21,312 $22,971 $23,135 $-1,823
 
Total* $0 $35,376 $35,376 $40,116 $40,316 $-4,940

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
11/15/1998 

08/01/2001 
100  07/01/1998 

08/01/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
08/01/2001 

06/26/2008 
100  08/01/2001 

06/26/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
10/04/2002 

06/25/2008 
100  10/04/2002 

06/25/2008 


Begin Construction Phase

End Construction Phase
 

 
 

 
03/01/2009 

11/15/2011 
100  05/14/2009 

08/01/2011 
-2 

Begin Closeout Phase

End Closeout Phase
 

 
 

 
11/15/2011 

11/15/2013 
50  08/01/2011 

07/01/2015 


-20 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 3421 3421

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.