Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
99 Widen to 4 Lanes With a Median (Segment 4) |
Description: Near Yuba City, Central Avenue to OżBannion Road. Widen to 4 lanes with a median.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Sutter |
City | Yuba City |
Zip Code | 95991 |
Senate District |
04 |
Assembly District | 02 |
Congressional District | 02 |
Caltrans District |
03 |
County/State Route | Sutter 99 |
Postmile Begin/End | 16.8 22.7 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 9.4 | |
Pavement Lane Miles | 12.4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Sung Moon | 530-740-4805 | sung_moon@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Sung Moon | 530-740-4805 | sung_moon@dot.ca.gov | |
Right of Way Phase |
Caltrans | Sung Moon | 530-740-4805 | sung_moon@dot.ca.gov | |
Construction Phase |
Caltrans | Sung Moon | 530-740-4805 | sung_moon@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,729 | $10,729 | ||||
IIP Augmentation |
$0 | $21,171 | $21,171 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $22,946 | $22,946 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $54,846 | $54,846 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $137 | $137 | $58 | $137 | $0 | |
Design(PS&E) |
$0 | $4,358 | $4,358 | $4,443 | $4,443 | $-85 | |
Right of Way |
$0 | $18,451 | $18,451 | $15,641 | $19,619 | $-1,168 | |
Construction |
$0 | $31,900 | $31,900 | $30,288 | $31,898 | $2 | |
Total* | $0 | $54,846 | $54,846 | $50,430 | $56,097 | $-1,251 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
06/01/1999 03/12/2004 |
|
06/01/1999 03/12/2004 |
100 | 03/12/2004 03/12/2004 |
-58 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/12/2004 07/01/2007 |
|
03/12/2004 03/19/2008 |
100 | 03/12/2004 03/19/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
04/01/2005 07/01/2007 |
|
04/01/2005 03/03/2008 |
100 | 04/01/2005 03/03/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2008 08/01/2011 |
|
07/28/2008 08/31/2011 |
100 | 07/28/2008 08/31/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
08/01/2011 08/01/2013 |
|
08/31/2011 12/01/2016 |
100 | 08/31/2011 12/01/2016 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 9.4 | |
Pavement Lane Miles | 12.4 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$31,900,000 |
Actual Expenditures: |
$30,522,770 |
Status as of December 31, 2023.