99 Widen to 4 Lanes With a Median (Segment 4)

Description: Near Yuba City, Central Avenue to OżBannion Road. Widen to 4 lanes with a median.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sutter
City Yuba City
Zip Code 95991
 
Senate District
04
Assembly District 02
Congressional District 02
 
Caltrans District
03
 
 
County/State Route Sutter 99
Postmile Begin/End 16.8 22.7
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)      9.4  
Pavement Lane Miles  12.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Sung Moon 530-740-4805   sung_moon@dot.ca.gov
Design (PS&E) Phase
Caltrans Sung Moon 530-740-4805   sung_moon@dot.ca.gov
Right of Way Phase
Caltrans Sung Moon 530-740-4805   sung_moon@dot.ca.gov
Construction Phase
Caltrans Sung Moon 530-740-4805   sung_moon@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,729 $10,729
IIP Augmentation
$0 $21,171 $21,171
Non-bond Funding
State/Federal*
$0 $22,946 $22,946
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $54,846 $54,846

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $137 $137 $58 $137 $0
Design(PS&E)
$0 $4,358 $4,358 $4,443 $4,443 $-85
Right of Way
$0 $18,451 $18,451 $15,641 $19,619 $-1,168
Construction
$0 $31,900 $31,900 $30,288 $31,898 $2
 
Total* $0 $54,846 $54,846 $50,430 $56,097 $-1,251

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
06/01/1999 

03/12/2004 
 

 
06/01/1999 

03/12/2004 
100  03/12/2004 

03/12/2004 
-58 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/12/2004 

07/01/2007 
 

 
03/12/2004 

03/19/2008 
100  03/12/2004 

03/19/2008 


Begin Right of Way Phase

End Right of Way Phase
04/01/2005 

07/01/2007 
 

 
04/01/2005 

03/03/2008 
100  04/01/2005 

03/03/2008 


Begin Construction Phase

End Construction Phase
04/01/2008 

08/01/2011 
 

 
07/28/2008 

08/31/2011 
100  07/28/2008 

08/31/2011 


Begin Closeout Phase

End Closeout Phase
08/01/2011 

08/01/2013 
 

 
08/31/2011 

12/01/2016 
100  08/31/2011 

12/01/2016 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 9.4
Pavement Lane Miles 12.4

Bond Funding Cost
Adopted:
$0
Current Approved:
$31,900,000
Actual Expenditures:
$30,522,770

 

Status as of December 31, 2023.