Route 99/Whitmore Avenue Interchange

Description: In Ceres on Route 99 at Whitmore Avenue. Construct over crossing.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Stanislaus
City Ceres
Zip Code 95307
 
Senate District
12
Assembly District 26
Congressional District 18
 
Caltrans District
10
 
 
County/State Route Stanislaus 99
Postmile Begin/End 11.9 11.9
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  3425.5      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Christina Hibbard (209) 948-7889   Christina.Hibbard@dot.ca.gov
Design (PS&E) Phase
Caltrans Christina Hibbard (209) 948-7889   Christina.Hibbard@dot.ca.gov
Right of Way Phase
Caltrans Christina Hibbard (209) 948-7889   Christina.Hibbard@dot.ca.gov
Construction Phase
Caltrans Christina Hibbard (209) 948-7889   Christina.Hibbard@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $22,055 $22,055
Non-bond Funding
State/Federal*
$0 $19,876 $19,876
Local**
$0 $45 $45
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $41,976 $41,976

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $615 $615 $614 $614 $1
Design(PS&E)
$0 $2,781 $2,781 $3,023 $3,023 $-242
Right of Way
$0 $16,480 $16,480 $16,317 $16,317 $163
Construction
$0 $22,100 $22,100 $22,736 $22,829 $-729
 
Total* $0 $41,976 $41,976 $42,689 $42,782 $-806

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
07/01/1999 

07/23/2001 
100  07/01/1999 

07/23/2001 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
07/23/2001 

06/07/2007 
100  07/23/2001 

06/07/2007 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
07/23/2001 

06/06/2007 
100  07/23/2001 

06/06/2007 


Begin Construction Phase

End Construction Phase
 

 
 

 
06/23/2008 

06/23/2011 
50  06/23/2008 

06/23/2011 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
07/31/2011 

08/31/2013 
100  07/31/2011 

08/31/2013 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 3425.5

Bond Funding Cost
Adopted:
$0
Current Approved:
$41,976,000
Actual Expenditures:
$41,807,813

 

Status as of December 31, 2023.