Mooney Boulevard Widening

Description: In the city of Visalia on Route 63 from Packwood Creek to Route 198. Widen to six-lane conventional and improve channelization.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Visalia
Zip Code 93277
 
Senate District
18
Assembly District 34
Congressional District 21
 
Caltrans District
06
 
 
County/State Route Tulare 63
Postmile Begin/End 5.8 8
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Victor Shaw 559-243-3441   Victor_shaw@dot.ca.gov
Design (PS&E) Phase
Caltrans Victor Shaw 559-243-3441   Victor_shaw@dot.ca.gov
Right of Way Phase
Caltrans Victor Shaw 559-243-3441   Victor_shaw@dot.ca.gov
Construction Phase
Caltrans Victor Shaw 559-243-3441   Victor_shaw@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $13,317 $13,317
Non-bond Funding
State/Federal*
$0 $13,799 $13,799
Local**
$0 $0 $0
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $27,116 $27,116

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $947 $947 $956 $956 $-9
Design(PS&E)
$0 $3,305 $3,305 $3,655 $3,655 $-350
Right of Way
$0 $9,547 $9,547 $11,651 $12,006 $-2,459
Construction
$0 $13,317 $13,317 $13,973 $19,741 $-6,424
 
Total* $0 $27,116 $27,116 $30,235 $36,358 $-9,242

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1998 

05/23/2002 
07/01/1993 

05/23/2002 
07/01/1998 

05/23/2002 
100  07/01/1998 

05/23/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2002 

03/23/2007 
07/01/2002 

03/23/2007 
07/01/2002 

03/23/2007 
100  07/01/2002 

03/23/2007 


Begin Right of Way Phase

End Right of Way Phase
07/01/2002 

09/26/2007 
08/26/2007 

09/25/2007 
07/01/2002 

09/26/2007 
100  07/01/2002 

09/26/2007 


Begin Construction Phase

End Construction Phase
04/10/2008 

10/13/2010 
04/10/2008 

10/13/2010 
04/10/2008 

10/13/2010 
100  04/10/2008 

10/13/2010 


Begin Closeout Phase

End Closeout Phase
11/11/2010 

04/01/2012 
11/11/2010 

06/30/2010 
11/11/2010 

04/01/2012 
100  11/11/2010 

04/01/2013 


-12 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 4

Bond Funding Cost
Adopted:
$0
Current Approved:
$11,560,000
Actual Expenditures:
$10,520,000

 

Status as of December 31, 2023.