Mooney Boulevard Widening |
Description: In the city of Visalia on Route 63 from Packwood Creek to Route 198. Widen to six-lane conventional and improve channelization.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Tulare |
City | Visalia |
Zip Code | 93277 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 21 |
Caltrans District |
06 |
County/State Route | Tulare 63 |
Postmile Begin/End | 5.8 8 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Victor Shaw | 559-243-3441 | Victor_shaw@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Victor Shaw | 559-243-3441 | Victor_shaw@dot.ca.gov | |
Right of Way Phase |
Caltrans | Victor Shaw | 559-243-3441 | Victor_shaw@dot.ca.gov | |
Construction Phase |
Caltrans | Victor Shaw | 559-243-3441 | Victor_shaw@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $13,317 | $13,317 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $13,799 | $13,799 | ||||
Local** |
$0 | $0 | $0 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $27,116 | $27,116 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $947 | $947 | $956 | $956 | $-9 | |
Design(PS&E) |
$0 | $3,305 | $3,305 | $3,655 | $3,655 | $-350 | |
Right of Way |
$0 | $9,547 | $9,547 | $11,651 | $12,006 | $-2,459 | |
Construction |
$0 | $13,317 | $13,317 | $13,973 | $19,741 | $-6,424 | |
Total* | $0 | $27,116 | $27,116 | $30,235 | $36,358 | $-9,242 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/1998 05/23/2002 |
07/01/1993 05/23/2002 |
07/01/1998 05/23/2002 |
100 | 07/01/1998 05/23/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
07/01/2002 03/23/2007 |
07/01/2002 03/23/2007 |
07/01/2002 03/23/2007 |
100 | 07/01/2002 03/23/2007 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
07/01/2002 09/26/2007 |
08/26/2007 09/25/2007 |
07/01/2002 09/26/2007 |
100 | 07/01/2002 09/26/2007 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/10/2008 10/13/2010 |
04/10/2008 10/13/2010 |
04/10/2008 10/13/2010 |
100 | 04/10/2008 10/13/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
11/11/2010 04/01/2012 |
11/11/2010 06/30/2010 |
11/11/2010 04/01/2012 |
100 | 11/11/2010 04/01/2013 |
0 -12 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$11,560,000 |
Actual Expenditures: |
$10,520,000 |
Status as of December 31, 2023.