Route 99/145 Interchange Improvements |
Description: In the city of Madera on Route 145 at Route 99. Improve approaches to interchange and bridge over Route 99.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Madera |
City | Madera |
Zip Code | 93638 |
Senate District |
12 |
Assembly District | 25 |
Congressional District | 18 |
Caltrans District |
06 |
County/State Route | Madera 145 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 12000 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
CT | Richard Putler | (559) 445-5286 | richard.putler@dot.ca.gov | |
Design (PS&E) Phase |
CT | Ernie Penuna | (559) 230-3142 | ernie.penuna@dot.ca.gov | |
Right of Way Phase |
CT | David Sherman | (559) 445-6225 | david.sherman@dot.ca.gov | |
Construction Phase |
CT | Alberto Lopez | (559) 243-3818 | alberto.lopez@dot.ca.gov | |
Corridor System Management Plan |
CT | Gail Miller | 559-488-4115 | gail.miller@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $4,309 | $4,309 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $300 | $300 | ||||
Local** |
$0 | $3,499 | $3,499 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $8,108 | $8,108 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $121 | $121 | $0 | $0 | $121 | |
Design(PS&E) |
$0 | $676 | $676 | $599 | $599 | $77 | |
Right of Way |
$0 | $602 | $602 | $0 | $0 | $602 | |
Construction |
$0 | $6,709 | $6,709 | $8,266 | $8,266 | $-1,557 | |
Total* | $0 | $8,108 | $8,108 | $8,865 | $8,865 | $-757 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
10/24/2008 |
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
03/31/2009 10/01/2012 |
0 | 03/31/2009 10/01/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/07/2010 07/01/2014 |
0 | 07/01/2014 11/14/2013 |
-43 8 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Peak Period Time Savings (minutes) | 12000 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.