Route 99/145 Interchange Improvements

Description: In the city of Madera on Route 145 at Route 99. Improve approaches to interchange and bridge over Route 99.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Madera
City Madera
Zip Code 93638
 
Senate District
12
Assembly District 25
Congressional District 18
 
Caltrans District
06
 
 
County/State Route Madera 145
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  12000      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
CT Richard Putler (559) 445-5286   richard.putler@dot.ca.gov
Design (PS&E) Phase
CT Ernie Penuna (559) 230-3142   ernie.penuna@dot.ca.gov
Right of Way Phase
CT David Sherman (559) 445-6225   david.sherman@dot.ca.gov
Construction Phase
CT Alberto Lopez (559) 243-3818   alberto.lopez@dot.ca.gov
 
Corridor System Management Plan
CT Gail Miller 559-488-4115   gail.miller@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $4,309 $4,309
Non-bond Funding
State/Federal*
$0 $300 $300
Local**
$0 $3,499 $3,499
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $8,108 $8,108

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $121 $121 $0 $0 $121
Design(PS&E)
$0 $676 $676 $599 $599 $77
Right of Way
$0 $602 $602 $0 $0 $602
Construction
$0 $6,709 $6,709 $8,266 $8,266 $-1,557
 
Total* $0 $8,108 $8,108 $8,865 $8,865 $-757

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

10/24/2008 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
03/31/2009 

10/01/2012 
03/31/2009 

10/01/2012 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/07/2010 

07/01/2014 
07/01/2014 

11/14/2013 
-43 

????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 12000

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.