Manzanar / Independence 4-Lane |
Description: Near Independence from 0.6 mile south of Los Angeles Aqueduct Bridge #48-14 to 0.4 mile north of Shabbell Lane. Widen to a four-lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Inyo |
City | Independence |
Zip Code | 93514 |
Senate District |
18 |
Assembly District | 34 |
Congressional District | 25 |
Caltrans District |
09 |
County/State Route | Inyo 395 |
Postmile Begin/End | 65 76.1 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 16 | 22.2 |
Rehabilitated Lane Miles (miles) | 16 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
California Department of Transportation | Bryan Winzenread | (760)872-3143 | Bryan_Winzenread@dot.ca.gov | |
Design (PS&E) Phase |
California Department of Transportation | Bryan Winzenread | (760)872-3143 | Bryan_Winzenread@dot.ca.gov | |
Right of Way Phase |
California Department of Transportation | Bryan Winzenread | (760)872-3143 | Bryan_Winzenread@dot.ca.gov | |
Construction Phase |
California Department of Transportation | Bryan Winzenread | (760)872-3143 | Bryan_Winzenread@dot.ca.gov | |
Corridor System Management Plan |
California Department of Transportation | Bryan Winzenread | (760)872-3143 | Bryan_Winzenread@dot.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$11,608 | $0 | $11,608 | ||||
IIP Augmentation |
$35,928 | $0 | $35,928 | ||||
Non-bond Funding | |||||||
State/Federal* |
$2,795 | $23,199 | $25,994 | ||||
Total**** | $50,331 | $23,199 | $73,530 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $4,968 | $4,968 | $3,150 | $3,150 | $1,818 | |
Design(PS&E) |
$0 | $6,675 | $6,675 | $3,829 | $3,829 | $2,846 | |
Right of Way |
$0 | $6,195 | $6,195 | $3,561 | $3,561 | $2,634 | |
Construction |
$50,331 | $5,361 | $55,692 | $44,632 | $45,028 | $10,664 | |
Total* | $50,331 | $23,199 | $73,530 | $55,173 | $55,569 | $17,961 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
07/01/1998 04/15/2004 |
01/09/2008 01/09/2008 |
07/01/1998 05/13/2004 |
100 | 07/01/1998 05/13/2004 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
03/15/2002 07/01/2007 |
01/09/2008 01/09/2008 |
08/20/2003 07/01/2007 |
100 | 04/15/2004 06/29/2007 |
-7 0 |
Begin Right of Way Phase
End Right of Way Phase |
09/21/2004 01/01/2008 |
01/09/2008 01/09/2008 |
09/21/2004 01/01/2008 |
100 | 09/21/2004 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/01/2008 01/01/2011 |
01/09/2008 01/09/2008 |
06/01/2008 01/01/2011 |
100 | 06/01/2008 11/16/2010 |
0 2 |
Begin Closeout Phase
End Closeout Phase |
01/01/2011 01/01/2012 |
01/09/2008 01/09/2008 |
01/02/2011 01/01/2012 |
50 | 11/16/2010 12/20/2016 |
2 -60 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 16 | 22.2 |
Rehabilitated Lane Miles (miles) | 16 |
Bond Funding Cost | |
---|---|
Adopted: |
$47,536,000 |
Current Approved: |
$45,000,000 |
Actual Expenditures: |
$38,693,605 |
Status as of December 31, 2023.