Caltrans Logo

Manzanar / Independence 4-Lane

Description: Near Independence from 0.6 mile south of Los Angeles Aqueduct Bridge #48-14 to 0.4 mile north of Shabbell Lane. Widen to a four-lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Inyo
City Independence
Zip Code 93514
 
Senate District
18
Assembly District 34
Congressional District 25
 
Caltrans District
09
 
 
County/State Route Inyo 395
Postmile Begin/End 65 76.1
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  16    22.2  
Rehabilitated Lane Miles (miles)  16      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
California Department of Transportation Bryan Winzenread (760)872-3143   Bryan_Winzenread@dot.ca.gov
Design (PS&E) Phase
California Department of Transportation Bryan Winzenread (760)872-3143   Bryan_Winzenread@dot.ca.gov
Right of Way Phase
California Department of Transportation Bryan Winzenread (760)872-3143   Bryan_Winzenread@dot.ca.gov
Construction Phase
California Department of Transportation Bryan Winzenread (760)872-3143   Bryan_Winzenread@dot.ca.gov
 
Corridor System Management Plan
California Department of Transportation Bryan Winzenread (760)872-3143   Bryan_Winzenread@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$11,608 $0 $11,608
IIP Augmentation
$35,928 $0 $35,928
Non-bond Funding
State/Federal*
$2,795 $23,199 $25,994
 
Total**** $50,331 $23,199 $73,530

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $4,968 $4,968 $3,150 $3,150 $1,818
Design(PS&E)
$0 $6,675 $6,675 $3,829 $3,829 $2,846
Right of Way
$0 $6,195 $6,195 $3,561 $3,561 $2,634
Construction
$50,331 $5,361 $55,692 $44,632 $45,028 $10,664
 
Total* $50,331 $23,199 $73,530 $55,173 $55,569 $17,961

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1998 

04/15/2004 
01/09/2008 

01/09/2008 
07/01/1998 

05/13/2004 
100  07/01/1998 

05/13/2004 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
03/15/2002 

07/01/2007 
01/09/2008 

01/09/2008 
08/20/2003 

07/01/2007 
100  04/15/2004 

06/29/2007 
-7 

Begin Right of Way Phase

End Right of Way Phase
09/21/2004 

01/01/2008 
01/09/2008 

01/09/2008 
09/21/2004 

01/01/2008 
100  09/21/2004 

 


Begin Construction Phase

End Construction Phase
04/01/2008 

01/01/2011 
01/09/2008 

01/09/2008 
06/01/2008 

01/01/2011 
100  06/01/2008 

11/16/2010 


Begin Closeout Phase

End Closeout Phase
01/01/2011 

01/01/2012 
01/09/2008 

01/09/2008 
01/02/2011 

01/01/2012 
50  11/16/2010 

12/20/2016 


-60 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 16 22.2
Rehabilitated Lane Miles (miles) 16

Bond Funding Cost
Adopted:
$47,536,000
Current Approved:
$45,000,000
Actual Expenditures:
$38,693,605

 

Status as of December 31, 2023.