Darrah Road Rehabilitation |
Description: Near Mariposa on Darrah Road from Route 49 South to Triangle Road. Rehabilitate roadway, minor realignment and shoulder work.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Mariposa |
City | Mariposa |
Zip Code | 95338 |
Senate District |
14 |
Assembly District | 25 |
Congressional District | 19 |
Caltrans District |
10 |
County/State Route | Mariposa 49 |
Postmile Begin/End | 10 15 |
County/State Route | Mariposa 49 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 4.98 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Not Applicable | Not Applicable | (916) 691-0359 | Melissa.Ramos@cdcr.ca.gov | |
Design (PS&E) Phase |
Mariposa County Local Transportation Commition | Melissa Ramos | (916) 691-0359 | Melissa.Ramos@cdcr.ca.gov | |
Right of Way Phase |
Not Applicable | Not Applicable | (916) 691-0359 | Melissa.Ramos@cdcr.ca.gov | |
Construction Phase |
Mariposa County Local Transportation Commition | Melissa Ramos | (916) 691-0359 | Melissa.Ramos@cdcr.ca.gov | |
Corridor System Management Plan |
Not Applicable | Not Applicable | (916) 691-0359 | Melissa.Ramos@cdcr.ca.gov |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $1,085 | $1,085 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $35 | $35 | ||||
Total**** | $0 | $1,120 | $1,120 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $0 | $0 | $0 | |
Design(PS&E) |
$0 | $70 | $70 | $0 | $0 | $70 | |
Right of Way |
$0 | $0 | $0 | $0 | $0 | $0 | |
Construction |
$0 | $1,050 | $1,050 | $916 | $1,832 | $-782 | |
Total* | $0 | $1,120 | $1,120 | $916 | $1,832 | $-712 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
09/20/2007 03/30/2008 |
|
10/17/2007 02/10/2009 |
100 | 10/17/2007 02/10/2009 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Rehabilitated Lane Miles (miles) | 4.98 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.