Caltrans Logo

I-680 Southbound HOT Lane Integrator

Description: From Milpitas to near Pleasanton, on Route 680. Southbound HOT accommodation.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Alameda, Santa Clara
City Fremont, Milpitas, Pleasanton
Zip Code 94536, 94566, 95035
 
Senate District
10
Assembly District 18, 20
Congressional District 11, 13
 
Caltrans District
04
 
 
County/State Route Alameda 680
Postmile Begin/End 0 11.5
 
County/State Route Santa Clara 680
Postmile Begin/End 7.5 9.9
Project Benefits
 Benefit Baseline Actual
Peak Period Time Savings (minutes)  17      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
ACTC Stewart Ng (510)208-7437   stewartng@alamedactc.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $8,000 $8,000
Non-bond Funding
State/Federal*
$0 $3,464 $3,464
Local**
$0 $7,483 $7,483
 
Total**** $0 $18,947 $18,947

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $2,882 $2,882 $2,882 $2,882 $0
Design(PS&E)
$0 $3,387 $3,387 $3,387 $3,387 $0
Right of Way
$0 $0 $0 $0 $0 $0
Construction
$0 $12,678 $12,678 $12,678 $12,678 $0
 
Total* $0 $18,947 $18,947 $18,947 $18,947 $0

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

03/26/2006 
 

03/26/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

06/30/2008 
 

06/30/2008 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

06/30/2008 
 

06/30/2008 


Begin Construction Phase

End Construction Phase
 

 
 

 
12/15/2008 

06/11/2013 
100  12/15/2008 

04/30/2012 


14 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
06/11/2013 

12/11/2013 
04/30/2012 

10/30/2012 
14 

14 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Peak Period Time Savings (minutes) 17

Bond Funding Cost
Adopted:
$0
Current Approved:
$8,000,000
Actual Expenditures:
$8,000,000

Click to view the Final Audit Report

 

Status as of December 31, 2023.