Caltrans Logo

Route 10 HOV Lanes from Route 605 to Puente Avenue

Description: In Baldwin Park, on Route 10 from Route 605 to Puente Avenue. Construct one HOV lane in each direction. (TCRP #40).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Los Angeles
City Baldwin Park
Zip Code 91706
 
Senate District
24
Assembly District 57
Congressional District 32
 
Caltrans District
07
 
 
County/State Route Los Angeles 10
Postmile Begin/End 31.2 33.4
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (HOV)  4.4    4.2  
Lane Miles Added (Mixed)      0  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Gary Iverson (213) 897-3818   gary_iverson@dot.ca.gov
Design (PS&E) Phase
Caltrans Refugio Dominguez (213) 897-5580   refugio_dominguez@dot.ca.gov
Right of Way Phase
Caltrans Dan Murdoch (213) 897-1816   dan_murduch@dot.ca.gov
Construction Phase
Caltrans Mehdi Salehinik (213) 897-7195   mehdi_salehinik@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $74,393 $74,393
Non-bond Funding
State/Federal*
$0 $71,360 $71,360
Local**
$0 $62,811 $62,811
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $208,564 $208,564

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $3,542 $3,542 $1,847 $1,847 $1,695
Design(PS&E)
$0 $13,015 $13,015 $13,569 $13,569 $-554
Right of Way
$0 $55,763 $55,763 $52,521 $54,865 $898
Construction
$0 $136,244 $136,244 $166,474 $166,474 $-30,230
 
Total* $0 $208,564 $208,564 $234,411 $236,756 $-28,192

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
09/01/1995 

12/31/2002 
 

 
09/01/1995 

12/31/2002 
100  09/01/1995 

12/31/2002 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
01/01/2004 

03/27/2008 
 

 
01/01/2004 

03/27/2008 
100  01/01/2004 

03/27/2008 


Begin Right of Way Phase

End Right of Way Phase
01/01/2004 

03/21/2008 
 

 
01/01/2004 

03/21/2008 
100  01/01/2004 

03/21/2008 


Begin Construction Phase

End Construction Phase
04/30/2009 

02/04/2016 
 

 
04/30/2009 

02/04/2016 
04/30/2009 

02/04/2016 


Begin Closeout Phase

End Closeout Phase
02/02/2018 

07/15/2021 
 

 
02/02/2018 

07/15/2021 
90  02/02/2018 

03/16/2021 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (HOV) 4.4 4.2
Lane Miles Added (Mixed) 0

Bond Funding Cost
Adopted:
$0
Current Approved:
$74,393,000
Actual Expenditures:
$74,246,000

 

Status as of December 31, 2023.