Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Route 10 HOV Lanes from Route 605 to Puente Avenue |
Description: In Baldwin Park, on Route 10 from Route 605 to Puente Avenue. Construct one HOV lane in each direction. (TCRP #40).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Los Angeles |
City | Baldwin Park |
Zip Code | 91706 |
Senate District |
24 |
Assembly District | 57 |
Congressional District | 32 |
Caltrans District |
07 |
County/State Route | Los Angeles 10 |
Postmile Begin/End | 31.2 33.4 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 4.4 | 4.2 |
Lane Miles Added (Mixed) | 0 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Gary Iverson | (213) 897-3818 | gary_iverson@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Refugio Dominguez | (213) 897-5580 | refugio_dominguez@dot.ca.gov | |
Right of Way Phase |
Caltrans | Dan Murdoch | (213) 897-1816 | dan_murduch@dot.ca.gov | |
Construction Phase |
Caltrans | Mehdi Salehinik | (213) 897-7195 | mehdi_salehinik@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $74,393 | $74,393 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $71,360 | $71,360 | ||||
Local** |
$0 | $62,811 | $62,811 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $208,564 | $208,564 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $3,542 | $3,542 | $1,847 | $1,847 | $1,695 | |
Design(PS&E) |
$0 | $13,015 | $13,015 | $13,569 | $13,569 | $-554 | |
Right of Way |
$0 | $55,763 | $55,763 | $52,521 | $54,865 | $898 | |
Construction |
$0 | $136,244 | $136,244 | $166,474 | $166,474 | $-30,230 | |
Total* | $0 | $208,564 | $208,564 | $234,411 | $236,756 | $-28,192 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
09/01/1995 12/31/2002 |
|
09/01/1995 12/31/2002 |
100 | 09/01/1995 12/31/2002 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
01/01/2004 03/27/2008 |
|
01/01/2004 03/27/2008 |
100 | 01/01/2004 03/27/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
01/01/2004 03/21/2008 |
|
01/01/2004 03/21/2008 |
100 | 01/01/2004 03/21/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
04/30/2009 02/04/2016 |
|
04/30/2009 02/04/2016 |
0 | 04/30/2009 02/04/2016 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
02/02/2018 07/15/2021 |
|
02/02/2018 07/15/2021 |
90 | 02/02/2018 03/16/2021 |
0 4 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (HOV) | 4.4 | 4.2 |
Lane Miles Added (Mixed) | 0 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$74,393,000 |
Actual Expenditures: |
$74,246,000 |
Status as of December 31, 2023.