Highway 25 Safety and Operational Enhancements

Description: In Hollister, on Route 25 from Hudner Lane to the Santa Clara county line. Construct concrete median barrier, consolidate private driveways, ad limit access.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Benito
City Hollister
Zip Code 95023
 
Senate District
12
Assembly District 28
Congressional District 17
 
Caltrans District
05
 
 
County/State Route San Benito 25
Postmile Begin/End 52.8 60
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles  12.4      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
 
Right of Way Phase
 
Construction Phase
San Benito Council of Governments Mary Dinkuhn (831) 637-7665   maryd@sanbenitocog.org
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,825 $10,825
Non-bond Funding
Local**
$0 $2,497 $2,497
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $13,322 $13,322

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $283 $283 $0 $0 $283
Design(PS&E)
$0 $1,864 $1,864 $11 $11 $1,853
Right of Way
$0 $350 $350 $0 $0 $350
Construction
$0 $10,825 $10,825 $10,102 $10,102 $723
 
Total* $0 $13,322 $13,322 $10,113 $10,113 $3,209

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
05/14/2009 

10/22/2010 
 

 
05/14/2009 

10/22/2010 
100  05/14/2009 

10/22/2010 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
75   

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles 12.4

Bond Funding Cost
Adopted:
$0
Current Approved:
$10,825,000
Actual Expenditures:
$10,092,818

 

Status as of December 31, 2023.