Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Highway 25 Safety and Operational Enhancements |
Description: In Hollister, on Route 25 from Hudner Lane to the Santa Clara county line. Construct concrete median barrier, consolidate private driveways, ad limit access.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Benito |
City | Hollister |
Zip Code | 95023 |
Senate District |
12 |
Assembly District | 28 |
Congressional District | 17 |
Caltrans District |
05 |
County/State Route | San Benito 25 |
Postmile Begin/End | 52.8 60 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | 12.4 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
|||||
Right of Way Phase |
|||||
Construction Phase |
San Benito Council of Governments | Mary Dinkuhn | (831) 637-7665 | maryd@sanbenitocog.org | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,825 | $10,825 | ||||
Non-bond Funding | |||||||
Local** |
$0 | $2,497 | $2,497 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $13,322 | $13,322 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $283 | $283 | $0 | $0 | $283 | |
Design(PS&E) |
$0 | $1,864 | $1,864 | $11 | $11 | $1,853 | |
Right of Way |
$0 | $350 | $350 | $0 | $0 | $350 | |
Construction |
$0 | $10,825 | $10,825 | $10,102 | $10,102 | $723 | |
Total* | $0 | $13,322 | $13,322 | $10,113 | $10,113 | $3,209 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
05/14/2009 10/22/2010 |
|
05/14/2009 10/22/2010 |
100 | 05/14/2009 10/22/2010 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
75 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | 12.4 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$10,825,000 |
Actual Expenditures: |
$10,092,818 |
Status as of December 31, 2023.