New Route 905 Freeway - Otay Mesa

Description: Near San Diego ¿ From Britannia Boulevard to Siempre Viva Interchange ¿ Construct 6-lane freeway (Phase 1A-Eastern Segment of Stage 1).

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Diego
City San Diego
Zip Code 92154
 
Senate District
40
Assembly District 79
Congressional District 51
 
Caltrans District
11
 
 
County/State Route San Diego 905
Postmile Begin/End R  8.6 R  11.6
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  18    18  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Design (PS&E) Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Right of Way Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
Construction Phase
Caltrans Ismael Salazar (619) 688-6766   Ismael_Salazar@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $10,237 $10,237
IIP Augmentation
$0 $75,073 $75,073
Non-bond Funding
State/Federal*
$0 $203,963 $203,963
Local**
$0 $60,585 $60,585
 
Total**** $0 $349,858 $349,858

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $2,771 $2,771 $6,331 $6,331 $-3,560
Design(PS&E)
$0 $18,850 $18,850 $24,920 $24,920 $-6,070
Right of Way
$0 $230,927 $230,927 $178,646 $324,564 $-93,637
Construction
$0 $97,310 $97,310 $86,602 $106,418 $-9,108
 
Total* $0 $349,858 $349,858 $296,499 $462,233 $-112,375

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
10/10/1996 

07/23/2004 
07/23/2004 

07/23/2004 
-94 

Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

09/18/2007 
09/18/2007 

01/16/2006 


20 
Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
01/16/2006 

 
100  01/16/2006 

04/22/2008 


Begin Construction Phase

End Construction Phase
 

 
 

 
04/22/2008 

06/30/2011 
06/30/2011 

12/25/2017 
-39 

-79 
Begin Closeout Phase

End Closeout Phase
 

 
 

 
12/25/2017 

10/23/2018 
12/25/2018 

12/20/2019 
-12 

-14 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 18 18

Bond Funding Cost
Adopted:
$0
Current Approved:
$85,310,000
Actual Expenditures:
$76,510,000

 

Status as of December 31, 2023.