New Route 905 Freeway - Otay Mesa |
Description: Near San Diego ¿ From Britannia Boulevard to Siempre Viva Interchange ¿ Construct 6-lane freeway (Phase 1A-Eastern Segment of Stage 1).
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Diego |
City | San Diego |
Zip Code | 92154 |
Senate District |
40 |
Assembly District | 79 |
Congressional District | 51 |
Caltrans District |
11 |
County/State Route | San Diego 905 |
Postmile Begin/End | R 8.6 R 11.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 18 | 18 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Ismael Salazar | (619) 688-6766 | Ismael_Salazar@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Ismael Salazar | (619) 688-6766 | Ismael_Salazar@dot.ca.gov | |
Right of Way Phase |
Caltrans | Ismael Salazar | (619) 688-6766 | Ismael_Salazar@dot.ca.gov | |
Construction Phase |
Caltrans | Ismael Salazar | (619) 688-6766 | Ismael_Salazar@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $10,237 | $10,237 | ||||
IIP Augmentation |
$0 | $75,073 | $75,073 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $203,963 | $203,963 | ||||
Local** |
$0 | $60,585 | $60,585 | ||||
Total**** | $0 | $349,858 | $349,858 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $2,771 | $2,771 | $6,331 | $6,331 | $-3,560 | |
Design(PS&E) |
$0 | $18,850 | $18,850 | $24,920 | $24,920 | $-6,070 | |
Right of Way |
$0 | $230,927 | $230,927 | $178,646 | $324,564 | $-93,637 | |
Construction |
$0 | $97,310 | $97,310 | $86,602 | $106,418 | $-9,108 | |
Total* | $0 | $349,858 | $349,858 | $296,499 | $462,233 | $-112,375 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
10/10/1996 07/23/2004 |
0 | 07/23/2004 07/23/2004 |
-94 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
09/18/2007 |
0 | 09/18/2007 01/16/2006 |
0 20 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
01/16/2006 |
100 | 01/16/2006 04/22/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
04/22/2008 06/30/2011 |
0 | 06/30/2011 12/25/2017 |
-39 -79 |
Begin Closeout Phase
End Closeout Phase |
|
|
12/25/2017 10/23/2018 |
0 | 12/25/2018 12/20/2019 |
-12 -14 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 18 | 18 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$85,310,000 |
Actual Expenditures: |
$76,510,000 |
Status as of December 31, 2023.