SLO Operational Improvements

Description: In Arroyo Grande and Pismo Beach, on Route 101 from 0.1 mile north of Route 227 to 0.8 mile north of Route 1. Operational improvements.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
San Luis Obispo
City Arroyo Grande
Zip Code 93420
 
Senate District
15
Assembly District 33
Congressional District 22, 23
 
Caltrans District
05
 
 
County/State Route San Luis Obispo 101
Postmile Begin/End 13.2 17.9
Project Benefits
 Benefit Baseline Actual
Additional Auxiliary Lane Miles  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Amy Donatello (805) 549-3014   amy.donatello@dot.ca.gov
Design (PS&E) Phase
Caltrans Amy Donatello (805) 549-3014   amy.donatello@dot.ca.gov
Right of Way Phase
Caltrans Amy Donatello (805) 549-3014   amy.donatello@dot.ca.gov
Construction Phase
Caltrans Amy Donatello (805) 549-3014   amy.donatello@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $4,774 $4,774
IIP Augmentation
$0 $4,683 $4,683
Non-bond Funding
State/Federal*
$0 $2,841 $2,841
 
Total**** $0 $12,298 $12,298

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $549 $549 $486 $486 $63
Design(PS&E)
$0 $2,102 $2,102 $2,247 $2,748 $-646
Right of Way
$0 $190 $190 $7 $8 $182
Construction
$0 $9,457 $9,457 $7,950 $7,950 $1,507
 
Total* $0 $12,298 $12,298 $10,690 $11,191 $1,107

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
10/01/2008 

06/30/2011 
100  10/01/2008 

06/30/2011 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
06/30/2011 

12/15/2011 
100  06/30/2011 

12/15/2011 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Auxiliary Lane Miles 2 2

Bond Funding Cost
Adopted:
$0
Current Approved:
$9,457
Actual Expenditures:
$7,924

 

Status as of December 31, 2023.