SLO Operational Improvements |
Description: In Arroyo Grande and Pismo Beach, on Route 101 from 0.1 mile north of Route 227 to 0.8 mile north of Route 1. Operational improvements.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
San Luis Obispo |
City | Arroyo Grande |
Zip Code | 93420 |
Senate District |
15 |
Assembly District | 33 |
Congressional District | 22, 23 |
Caltrans District |
05 |
County/State Route | San Luis Obispo 101 |
Postmile Begin/End | 13.2 17.9 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 2 | 2 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Amy Donatello | (805) 549-3014 | amy.donatello@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Amy Donatello | (805) 549-3014 | amy.donatello@dot.ca.gov | |
Right of Way Phase |
Caltrans | Amy Donatello | (805) 549-3014 | amy.donatello@dot.ca.gov | |
Construction Phase |
Caltrans | Amy Donatello | (805) 549-3014 | amy.donatello@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $4,774 | $4,774 | ||||
IIP Augmentation |
$0 | $4,683 | $4,683 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $2,841 | $2,841 | ||||
Total**** | $0 | $12,298 | $12,298 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $549 | $549 | $486 | $486 | $63 | |
Design(PS&E) |
$0 | $2,102 | $2,102 | $2,247 | $2,748 | $-646 | |
Right of Way |
$0 | $190 | $190 | $7 | $8 | $182 | |
Construction |
$0 | $9,457 | $9,457 | $7,950 | $7,950 | $1,507 | |
Total* | $0 | $12,298 | $12,298 | $10,690 | $11,191 | $1,107 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
|
|
10/01/2008 06/30/2011 |
100 | 10/01/2008 06/30/2011 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
06/30/2011 12/15/2011 |
100 | 06/30/2011 12/15/2011 |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Auxiliary Lane Miles | 2 | 2 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$9,457 |
Actual Expenditures: |
$7,924 |
Status as of December 31, 2023.