Westside Parkway - Phase I |
Description: In Bakersfield, from Route 58 to Truxtun Avenue. Construct new 4 lane and 6 lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | 93301 |
Senate District |
18 |
Assembly District | 32 |
Congressional District | 22 |
Caltrans District |
06 |
County/State Route | Kern 58 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Commuter Lines | 1 | |
Lane Miles Added (Mixed) | 6 | |
Pavement Lane Miles | 6 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Design (PS&E) Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Right of Way Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Construction Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Corridor System Management Plan |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $62,380 | $62,380 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $49,300 | $49,300 | ||||
Total**** | $0 | $111,680 | $111,680 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $2,700 | $2,700 | $3 | $6 | $2,694 | |
Design(PS&E) |
$0 | $14,500 | $14,500 | $25 | $50 | $14,450 | |
Right of Way |
$0 | $32,100 | $32,100 | $46 | $92 | $32,008 | |
Construction |
$0 | $62,380 | $62,380 | $35 | $70 | $62,310 | |
Total* | $0 | $111,680 | $111,680 | $109 | $217 | $111,463 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/28/2008 02/28/2009 |
|
03/30/2012 |
0 | 03/30/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Additional Commuter Lines | 1 | |
Lane Miles Added (Mixed) | 6 | |
Pavement Lane Miles | 6 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.