Westside Parkway - Phase I

Description: In Bakersfield, from Route 58 to Truxtun Avenue. Construct new 4 lane and 6 lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93301
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
 
County/State Route Kern 58
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Additional Commuter Lines  1      
Lane Miles Added (Mixed)  6      
Pavement Lane Miles  6      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Design (PS&E) Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Right of Way Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Construction Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
 
Corridor System Management Plan
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $62,380 $62,380
Non-bond Funding
State/Federal*
$0 $49,300 $49,300
 
Total**** $0 $111,680 $111,680

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $2,700 $2,700 $3 $6 $2,694
Design(PS&E)
$0 $14,500 $14,500 $25 $50 $14,450
Right of Way
$0 $32,100 $32,100 $46 $92 $32,008
Construction
$0 $62,380 $62,380 $35 $70 $62,310
 
Total* $0 $111,680 $111,680 $109 $217 $111,463

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/28/2008 

02/28/2009 
 

 
 

03/30/2012 
03/30/2012 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Additional Commuter Lines 1
Lane Miles Added (Mixed) 6
Pavement Lane Miles 6

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.