Westside Parkway-Phase II |
Description: In Bakersfield, from Mohawk Street to Coffee Road. Construct new 6 lane expressway.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | Bakersfield |
Zip Code | 93308 |
Senate District |
18 |
Assembly District | 32 |
Congressional District | 22 |
Caltrans District |
06 |
County/State Route | Kern 00 |
Postmile Begin/End |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | 3 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Design (PS&E) Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Right of Way Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Construction Phase |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us | |
Corridor System Management Plan |
City of Bakersfield | Luis Topete | 661-326-3478 | ltopete@bakersfieldcity.us |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $62,000 | $62,000 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $8,820 | $8,820 | ||||
Total**** | $0 | $70,820 | $70,820 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $3 | $6 | $-6 | |
Design(PS&E) |
$0 | $0 | $0 | $25 | $50 | $-50 | |
Right of Way |
$0 | $8,820 | $8,820 | $46 | $92 | $8,728 | |
Construction |
$0 | $62,000 | $62,000 | $110 | $219 | $61,781 | |
Total* | $0 | $70,820 | $70,820 | $183 | $367 | $70,453 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
|
|
|
0 | |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
|
|
|
0 | |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
|
|
|
0 | |
0 0 |
Begin Construction Phase
End Construction Phase |
08/28/2008 02/28/2009 |
|
12/30/2012 |
0 | 12/30/2012 |
0 0 |
Begin Closeout Phase
End Closeout Phase |
|
|
|
0 | |
0 0 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Pavement Lane Miles | 3 |
Bond Funding Cost | |
---|---|
Adopted: |
|
Current Approved: |
|
Actual Expenditures: |
Status as of December 31, 2023.