Caltrans Logo

Westside Parkway-Phase II

Description: In Bakersfield, from Mohawk Street to Coffee Road. Construct new 6 lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Kern
City Bakersfield
Zip Code 93308
 
Senate District
18
Assembly District 32
Congressional District 22
 
Caltrans District
06
 
 
County/State Route Kern 00
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Pavement Lane Miles  3      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Design (PS&E) Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Right of Way Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Construction Phase
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
 
Corridor System Management Plan
City of Bakersfield Luis Topete 661-326-3478   ltopete@bakersfieldcity.us
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $62,000 $62,000
Non-bond Funding
State/Federal*
$0 $8,820 $8,820
 
Total**** $0 $70,820 $70,820

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $3 $6 $-6
Design(PS&E)
$0 $0 $0 $25 $50 $-50
Right of Way
$0 $8,820 $8,820 $46 $92 $8,728
Construction
$0 $62,000 $62,000 $110 $219 $61,781
 
Total* $0 $70,820 $70,820 $183 $367 $70,453

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
08/28/2008 

02/28/2009 
 

 
 

12/30/2012 
12/30/2012 

 


Begin Closeout Phase

End Closeout Phase
 

 
 

 
 

 
 

 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Pavement Lane Miles 3

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.