Road 80 - Ave 304 to Ave 328

Description: Between Visalia and Dinuba, on Road 80 Expressway from Avenue 304 to Avenue 328. Widen to 4 lanes.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tulare
City Dinuba, Visalia
Zip Code 93277
 
Senate District
16, 18
Assembly District 30, 31, 34
Congressional District 21
 
Caltrans District
06
 
 
County/State Route Tulare 0
Postmile Begin/End
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  6      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
County of Tulare - Resource Management Agency Philip Slitor (559) 733-6291   pslitor@co.tulare.ca.us
Design (PS&E) Phase
County of Tulare - Resource Management Agency Philip Slitor (559) 733-6291   pslitor@co.tulare.ca.us
Right of Way Phase
County of Tulare - Resource Management Agency Philip Slitor (559) 733-6291   pslitor@co.tulare.ca.us
Construction Phase
County of Tulare - Resource Management Agency Philip Slitor (559) 733-6291   pslitor@co.tulare.ca.us
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $7,855 $7,855
Non-bond Funding
State/Federal*
$0 $18,712 $18,712
Local**
$0 $3,400 $3,400
 
Total**** $0 $29,967 $29,967

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $2,388 $2,388 $2,202 $2,202 $186
Design(PS&E)
$0 $4,307 $4,307 $3,943 $3,943 $364
Right of Way
$0 $12,417 $12,417 $13,990 $13,990 $-1,573
Construction
$0 $10,855 $10,855 $7,888 $7,888 $2,967
 
Total* $0 $29,967 $29,967 $28,023 $28,023 $1,944

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
07/01/1999 

10/05/2006 
 

 
07/01/1999 

10/05/2006 
07/01/1999 

10/05/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/14/2006 

06/03/2008 
 

 
12/14/2006 

06/03/2008 
12/14/2006 

06/03/2008 


Begin Right of Way Phase

End Right of Way Phase
12/14/2006 

06/03/2008 
 

 
12/14/2006 

06/03/2008 
100  12/14/2006 

06/03/2008 


Begin Construction Phase

End Construction Phase
07/29/2008 

09/29/2009 
 

 
07/29/2008 

09/29/2009 
25  07/29/2008 

09/29/2009 


Begin Closeout Phase

End Closeout Phase
09/29/2009 

03/22/2011 
 

 
09/29/2009 

03/22/2011 
09/29/2009 

03/22/2011 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 6

Bond Funding Cost
Adopted:
Current Approved:
Actual Expenditures:

 

Status as of December 31, 2023.