Ophir Road (Phase 1) |
Description: Near Oroville, on Route 70 from north of Ophir Road intersection to west of Route 162. Widen to 4 lanes and construct signals.
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Butte |
City | Oroville |
Zip Code | 95965 |
Senate District |
04 |
Assembly District | 02, 03 |
Congressional District | 02, 04 |
Caltrans District |
03 |
County/State Route | Butte 70 |
Postmile Begin/End | 11.6 13.6 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 | |
Peak Period Time Savings (minutes) | 15 | 15 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
|||||
Design (PS&E) Phase |
Caltrans | Raimund Yambao | 530-741-4001 | Raimund_Yambao@dot.ca.gov | |
Right of Way Phase |
Caltrans | Raimund Yambao | 530-741-4001 | Raimund_Yambao@dot.ca.gov | |
Construction Phase |
Caltrans | Raimund Yambao | 530-741-4001 | Raimund_Yambao@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
RIP Augmentation |
$0 | $3,026 | $3,026 | ||||
IIP Augmentation |
$0 | $4,583 | $4,583 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $7,352 | $7,352 | ||||
Local** |
$0 | $5,864 | $5,864 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $20,825 | $20,825 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $0 | $0 | $1,454 | $1,454 | $-1,454 | |
Design(PS&E) |
$0 | $2,000 | $2,000 | $2,280 | $2,280 | $-280 | |
Right of Way |
$0 | $8,716 | $8,716 | $6,232 | $6,552 | $2,164 | |
Construction |
$0 | $10,109 | $10,109 | $8,566 | $8,999 | $1,110 | |
Total* | $0 | $20,825 | $20,825 | $18,532 | $19,284 | $1,541 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
12/30/2005 |
|
12/30/2005 |
100 | 02/01/1999 12/30/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
12/30/2005 11/03/2008 |
|
12/30/2005 11/03/2008 |
100 | 12/30/2005 11/03/2008 |
0 0 |
Begin Right of Way Phase
End Right of Way Phase |
12/30/2005 10/20/2008 |
|
12/30/2005 10/20/2008 |
100 | 12/30/2005 10/20/2008 |
0 0 |
Begin Construction Phase
End Construction Phase |
08/12/2009 11/01/2010 |
|
08/12/2009 11/15/2011 |
100 | 08/12/2009 09/28/2012 |
0 -11 |
Begin Closeout Phase
End Closeout Phase |
09/28/2012 10/01/2014 |
|
09/28/2012 10/01/2014 |
100 | 09/28/2012 07/01/2021 |
0 -82 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 4 | |
Peak Period Time Savings (minutes) | 15 | 15 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$7,609,000 |
Actual Expenditures: |
$7,609,000 |
Status as of December 31, 2023.