Ophir Road (Phase 1)

Description: Near Oroville, on Route 70 from north of Ophir Road intersection to west of Route 162. Widen to 4 lanes and construct signals.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Butte
City Oroville
Zip Code 95965
 
Senate District
04
Assembly District 02, 03
Congressional District 02, 04
 
Caltrans District
03
 
 
County/State Route Butte 70
Postmile Begin/End 11.6 13.6
Project Benefits
 Benefit Baseline Actual
Lane Miles Added (Mixed)  4      
Peak Period Time Savings (minutes)  15    15  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
 
Design (PS&E) Phase
Caltrans Raimund Yambao 530-741-4001   Raimund_Yambao@dot.ca.gov
Right of Way Phase
Caltrans Raimund Yambao 530-741-4001   Raimund_Yambao@dot.ca.gov
Construction Phase
Caltrans Raimund Yambao 530-741-4001   Raimund_Yambao@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $3,026 $3,026
IIP Augmentation
$0 $4,583 $4,583
Non-bond Funding
State/Federal*
$0 $7,352 $7,352
Local**
$0 $5,864 $5,864
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $20,825 $20,825

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $0 $0 $1,454 $1,454 $-1,454
Design(PS&E)
$0 $2,000 $2,000 $2,280 $2,280 $-280
Right of Way
$0 $8,716 $8,716 $6,232 $6,552 $2,164
Construction
$0 $10,109 $10,109 $8,566 $8,999 $1,110
 
Total* $0 $20,825 $20,825 $18,532 $19,284 $1,541

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

12/30/2005 
 

 
 

12/30/2005 
100  02/01/1999 

12/30/2005 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
12/30/2005 

11/03/2008 
 

 
12/30/2005 

11/03/2008 
100  12/30/2005 

11/03/2008 


Begin Right of Way Phase

End Right of Way Phase
12/30/2005 

10/20/2008 
 

 
12/30/2005 

10/20/2008 
100  12/30/2005 

10/20/2008 


Begin Construction Phase

End Construction Phase
08/12/2009 

11/01/2010 
 

 
08/12/2009 

11/15/2011 
100  08/12/2009 

09/28/2012 


-11 
Begin Closeout Phase

End Closeout Phase
09/28/2012 

10/01/2014 
 

 
09/28/2012 

10/01/2014 
100  09/28/2012 

07/01/2021 


-82 
????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Lane Miles Added (Mixed) 4
Peak Period Time Savings (minutes) 15 15

Bond Funding Cost
Adopted:
$0
Current Approved:
$7,609,000
Actual Expenditures:
$7,609,000

 

Status as of December 31, 2023.