South Avenue Reconstruction

Description: Near Corning, north of South Ave overcrossing. Reconstruct interchange to improve capacity and operations.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tehama
City Corning
Zip Code 96021
 
Senate District
04
Assembly District 03
Congressional District 01
 
Caltrans District
02
 
 
County/State Route Tehama 5
Postmile Begin/End R  3.5 R  10
Project Benefits
 Benefit Baseline Actual
Ramp Widenings  2    2  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Wesley Stroud 530-225-2928   wesley.stroud@dot.ca.gov
Design (PS&E) Phase
Caltrans Steve Topal 530-225-3205   steve.topal@dot.ca.gov
Right of Way Phase
Caltrans Lisa Hernandez-Harvey 530-225-3201   lisa.harvey@dot.ca.gov
Construction Phase
Caltrans Jim Rogers 530-895-5245   jim.rogers@dot.ca.gov
 
Corridor System Management Plan
 
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $8,663 $8,663
Non-bond Funding
State/Federal*
$0 $4,128 $4,128
Non Budgeted ETC
$0 $0 $0
 
Total**** $0 $12,791 $12,791

**** Totals may not add up exactly to column amounts due to rounding

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
Cost Forecast
(12/31/2023
e
Cost
Variance
f=c-e
 
Environmental
$0 $530 $530 $535 $535 $-5
Design(PS&E)
$0 $1,693 $1,693 $1,745 $1,745 $-52
Right of Way
$0 $1,905 $1,905 $1,777 $1,777 $128
Construction
$0 $8,663 $8,663 $5,392 $5,392 $3,271
 
Total* $0 $12,791 $12,791 $9,448 $9,448 $3,343

Pre Construction Components Not Included

* Totals may not add up exactly to column amounts due to rounding

** Totals include all project funds

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
 

 
 

 
 

 
 

 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
 

 
 

 
 

 
 

 


Begin Right of Way Phase

End Right of Way Phase
 

 
 

 
 

 
 

 


Begin Construction Phase

End Construction Phase
 

 
 

 
03/18/2009 

12/31/2010 
100  04/22/2009 

12/31/2010 
-1 

Begin Closeout Phase

End Closeout Phase
 

 
 

 
01/02/2011 

12/15/2011 
100  01/02/2011 

12/15/2011 


????????

Pre Construction Phases Not Included

No map available at this time.

Project Benefits
Benefit Baseline Actual
Ramp Widenings 2 2

Bond Funding Cost
Adopted:
$0
Current Approved:
$5,852,000
Actual Expenditures:
$5,391,503

 

Status as of December 31, 2023.