Propositions
Lease Revenue Bonds
Featured Links
Proposition 1B
Bond Accountability
Route 46 Expressway - Segment 1 |
Description: Near Wasco, from Route 33 to east of Browns Materials Road. Convert to a 4 lane expressway. (TCRP #113)
|
- Project Information
- Contacts
- Cost by Fund Source
- Cost by Component
- Schedule
- Map
- Closeout Info
Project Location | |
---|---|
County |
Kern |
City | |
Zip Code | |
Senate District |
|
Assembly District | |
Congressional District | |
Caltrans District |
06 |
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 16.4 | 16.4 |
Peak Period Time Savings (minutes) | 1.38 | 1.38 |
Project Contacts | Agency | Contact Person | Telephone | ||
---|---|---|---|---|---|
Environmental Phase |
Caltrans | Mehran Akhavan | (559) 243-3442 | Mehran Akavan@dot.ca.gov | |
Design (PS&E) Phase |
Caltrans | Mehran Akhavan | (559) 243-3442 | Mehran Akavan@dot.ca.gov | |
Right of Way Phase |
Caltrans | Mehran Akhavan | (559) 243-3442 | Mehran Akavan@dot.ca.gov | |
Construction Phase |
Caltrans | Mehran Akhavan | (559) 243-3442 | Mehran Akavan@dot.ca.gov | |
Corridor System Management Plan |
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2 | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
|||||
Bond Funding | |||||||
IIP Augmentation |
$0 | $16,609 | $16,609 | ||||
Non-bond Funding | |||||||
State/Federal* |
$0 | $10,525 | $10,525 | ||||
Local** |
$0 | $18,896 | $18,896 | ||||
Non Budgeted ETC |
$0 | $0 | $0 | ||||
Total**** | $0 | $46,030 | $46,030 |
**** Totals may not add up exactly to column amounts due to rounding
Project Cost Baseline Summary (Dollars Shown are in Thousands) | |||||||
---|---|---|---|---|---|---|---|
Adopted Program (06/07/07) a |
Approved Changes (12/31/2023 b=c-a |
Current Approved (12/31/2023 c |
Cost to Date** (12/31/2023 d |
Cost Forecast (12/31/2023 e |
Cost Variance f=c-e |
||
Environmental |
$0 | $1,525 | $1,525 | $1,580 | $1,580 | $-55 | |
Design(PS&E) |
$0 | $1,910 | $1,910 | $2,712 | $2,712 | $-802 | |
Right of Way |
$0 | $7,090 | $7,090 | $8,612 | $8,612 | $-1,522 | |
Construction |
$0 | $35,505 | $35,505 | $27,520 | $28,328 | $7,177 | |
Total* | $0 | $46,030 | $46,030 | $40,424 | $41,232 | $4,798 |
Pre Construction Components Not Included
* Totals may not add up exactly to column amounts due to rounding
** Totals include all project funds
Project Schedule Baseline Summary | ||||||
---|---|---|---|---|---|---|
(Schedule Changes and Variances in Months) | Adopted Program (06/07/07) a |
Approved Changes (mm/dd/yyyy) b |
Current Approved (12/31/2023) c |
% Complete (12/31/2023) d |
Schedule Forecast (12/31/2023) e |
Schedule Variance (months) f=c-e |
Begin Environmental Phase
End Environmental Phase |
03/06/2003 02/12/2005 |
|
03/06/2003 02/12/2005 |
0 | 03/06/2003 02/12/2005 |
0 0 |
Begin Design (PS&E) Phase
End Design (PS&E) Phase |
06/14/2005 07/18/2008 |
|
06/14/2005 07/18/2008 |
0 | 06/14/2005 01/30/2009 |
0 -7 |
Begin Right of Way Phase
End Right of Way Phase |
08/14/2005 07/18/2008 |
|
08/14/2005 07/18/2008 |
100 | 08/14/2005 01/30/2009 |
0 -7 |
Begin Construction Phase
End Construction Phase |
11/01/2008 11/15/2011 |
|
11/01/2008 11/15/2011 |
50 | 09/17/2009 11/03/2011 |
-11 0 |
Begin Closeout Phase
End Closeout Phase |
11/15/2011 11/20/2013 |
|
11/15/2011 11/20/2013 |
0 | 11/03/2011 03/25/2014 |
0 -4 |
????????
Pre Construction Phases Not Included
No map available at this time.
Project Benefits | ||
---|---|---|
Benefit | Baseline | Actual |
Lane Miles Added (Mixed) | 16.4 | 16.4 |
Peak Period Time Savings (minutes) | 1.38 | 1.38 |
Bond Funding Cost | |
---|---|
Adopted: |
$0 |
Current Approved: |
$16,609,000 |
Actual Expenditures: |
$15,808,000 |
Status as of December 31, 2023.